论文部分内容阅读
针对一起发生在五强溪水电厂行政生活区,损坏办公楼电脑网卡及工业电视前端摄像头等器件的雷击事件,组织力量对雷击现场进行了勘测,列举了建筑物直击雷防护、引下接地系统、弱电线路及设备感应雷防护及屏蔽方面存在的薄弱环节,采取接闪、接地、分流、屏蔽及等电位等针对性的措施,对行政生活区建筑及内部设施进行了防护,该工程于2005年12月竣工至今防雷实施部分未发生雷击损坏建筑和设备事故,取得了良好的防雷效果。
In view of the lightning events occurring in the administrative living area of Wuqiangxi Hydropower Plant, the damaged computer network card of the office building and the front-facing camera of the industrial television, the organizers conducted surveys on the scene of the lightning strikes, and listed the direct lightning protection of the buildings and the grounding system, Weak lines and equipment sensing lightning protection and shielding aspects of the weak links, take the lightning, grounding, shunting, shielding and equipotential and other targeted measures to the administrative living area construction and internal facilities were protected, the project in 2005 Since the completion of the lightning protection in December, there was no lightning and lightning damage to buildings and equipment, and a good lightning protection effect was achieved.