我公司承担的纪念堂部分钢窗安装任务共计13樘,三种规格,均为6节拼装而成,钢窗高度和面积都很大,宽3.9~6米,高11.6~15.5米。安装工作面拥挤,上下里外立体交叉作业,窗下铜门尚未到货,需要悬空,工期要求配合墙面花岗石安装在18天内完工。在任务新、工期紧的情况下,我们利用外檐装修脚手架与墙面钢筋网焊接工序同时进行施工,胜利完成了任务。
The number of steel window installation tasks undertaken by our company is 13 in total. Three sizes are assembled in six sections. The height and area of steel windows are large, 3.9 to 6 meters wide and 11.6 to 15.5 meters high. The installation work surface is crowded, crossover operations from top to bottom inside and outside, the copper door under the window has not yet arrived, need to be vacant, and the construction period is required to be completed within 18 days with the installation of the wall granite. In the case of new missions and tight schedules, we have used externally mounted scaffolding and wall steel mesh welding processes for simultaneous construction and successfully completed the mission.