论文部分内容阅读
摘要:市政排水管道建设工程虽然施工工艺相对不太复杂,但是由于大多项目是在市区施工,环境复杂,既有的地下管线及电缆情况不明,在确保既有工程安全的前提下,还要考虑地上交通等因素的影响,导致施工难度增加,施工质量和工期往往无法保证。为此,本文根据多年来从事施工技术工作的经验,对市政排水管道工程施工技术进行了综合分析。
关键词:市政排水;施工;技术措施
Abstract: The municipal sewer road construction projects although the construction process is relatively less complex, but because most of the projects are in the urban construction, the environment is complex, both underground pipelines and cables is unknown, to ensure both the safety of the works under the premise, but also consider ground transportation, and other factors, led to the increase in the difficulty of construction, construction quality and duration often can not be guaranteed. In this paper, based on the experience for many years engaged in the construction work, the municipal drainage pipe construction technology integrated analysis.Key words: municipal drainage; construction; technical measures
中圖分类号:TE832文献标识码:A 文章编号:
前言
排水管网是城市重要的基础设施,在排水系统中占有举足轻重的地位。由于历史的原因,许多城市的派水管网建设大都滞后于水厂建设,存在诸如管线老化、管径偏小或布局不合理等问题,制约了排水企业的发展。为此近年来各地都投入了大量的建设资金对市区排水管网进行改造。排水系统是其服务区内其他工程设施得以正常使用的重要设施之一,确保其施工质量至关重要。
1铺设管道前的准备工作
1.1道路的拆除与恢复
城区管道施工时,将有一定数量的既有路面被破除。为保证施工安全和路基质量,施工时要求管道在道路上开挖时,根据施工图纸设计要求,计算出开口宽度,并用白漆标注出开挖线,用切割机将路面切断,表层的破碎沥青面层及路基渣层,由挖掘机开挖,路基稳定砂层合理堆放以备回用,余土由自卸车运至弃土场。管道施工完成后,沟槽回填质量将直接影响道路的质量和使用功能。
1.2地上、地下公用设施的保护
管道沟槽开挖时,应根据地质土层情况及时采用支撑,以免造成滑坡、塌方。开挖边坡及支撑形式要交项目监理审查,得到认可后方能施工。在建筑物、构筑物基础及电线杆、灯杆附近开挖时应上报防止其下沉或变形的措施、加固工程计算书及图纸,并交项目监理审批。
某些地段需要排水,以使开挖人员始终在干燥环境中工作。排水过程不得使地面产生过大的沉降,影响现场周围的建筑物、构筑物和其他公用设施的正常使用和安全。在建筑物、构筑物基础及电线杆、灯杆附近开挖,采用钢板桩加固。在高压线下开挖时,挖掘机要求不在电线正下方工作,必要时采用人工开挖。
2管道施工
2.1沟槽开挖与支护
土方的工作量占整个工程的很大比重,在开挖前逐一探明地下既有管道、电缆和其他构筑物的位置,将调查结果和处理方案送交业主和相关管理单位确认,以便进行相应的保护、迁移等措施,保证开挖工作持续进行。
2.2管道安装
2.2.1管材的选用和检查。管材及主要配件由选定的合格制造商提供,管材进场后,由施工方材料工程师对产品的质量进行验证。当外观检查不能确保管材的质量时,进行内、外压试验。进场的管子必须是经过专业实验室批量检验合格并取得检验合格报告的产品。2.2.2下管。根据测放的中心线,用细绳控制好管道的一侧边线。采用轮胎式吊车下管,吊车沿沟槽开行至距沟边缘1 m处,以避免沟壁坍塌,影响沟槽边坡的稳定。下管时用专用吊钩或柔性吊索,严禁用钢丝绳穿入管内起吊。同时有专人指挥,绑(套)管子应找好重心,平吊轻放,避免扰动基底管道相互碰撞。管节下入沟槽时,避免与槽壁支撑及槽下的管道相互碰撞,严格控制水平与方向。管道的安装一定要符合质量要求。
3管道位置偏移或积水
3.1产生原因
测量差错,施工走样和意外的避让原有构筑物,在平面上产生位置偏移,立面上产生积水甚至倒坡现象。
3.2预防措施
3.2.1防止测量和施工造成的病害措施主要有:施工前要认真按照施工测量规范和规程进行交接桩复测与保护;施工放样要结合水文地质条件,按照埋置深度和设计要求以及有关规定放样,且必须进行复测检验其误差符合要求后才能交付施工;施工时要严格按照样桩进行,沟槽和平基要做好轴线和纵坡测量验收。3.2.2施工过程中如意外遇到构筑物须避让时,应在适当的位置增设连接井,其间以直线连通,连接井转角应大于135°。
4管道渗漏水,闭水试验不合格
4.1产生原因
基础不均匀下沉,管材及其接口施工质量差、闭水段端头封堵不严密、井体施工质量差等原因均可产生漏水现象。
4.2防治措施
4.2.1管材质量差,存在裂缝或局部砼松散,抗渗能力差,容易产生漏水。因此要求:所用管材要有质量部门提供合格证和力学试验报告等资料;管材外观质量要求表面平整无松散露骨和蜂窝麻面形象,硬物轻敲管壁其响声清脆悦耳;安装前再次逐节检查,对已发现或有质量疑问的应弃之不用或经有效处理后方可使用。
4.2.2管接口填料及施工质量差,管道在外力作用下产生破损或接口开裂。防治措施:选用质量良好的接口填料并按试验配合比和合理的施工工艺组织施工;接口缝内要洁净,对水泥类填料接口还要预先湿润,而对油性的则预先干燥后刷冷底子油,再按照施工操作规程认真施工。
4.2.3管道基础条件不良将导致管道和基础出现不均匀沉陷,一般造成局部积水,严重时会出现管道断裂或接口开裂。预防措施是:认真按设计要求施工,确保管道基础的强度和稳定性,当地基地质水文条件不良时,应进行换土改良处治,以提高基槽底部的承载力;如果槽底土壤被扰动或受水浸泡,应先挖除松软土层后和超挖部分用砂或碎石等稳定性好的材料回填密实。
4.2.4检查井施工质量差,井壁和与其连接管的结合处渗漏,预防措施:检查井砌筑砂浆要饱满,勾缝全面不遗漏;抹面前清洁和湿润表面,抹面时及时压光收浆并养护;遇有地下水时,抹面和勾缝应随砌筑及时完成,不可在回填以后再进行内抹面或内勾缝;与检查井连接的管外表面应先湿润且均匀刷一层水泥原浆,并座浆就位后再做好内外抹面,以防渗漏。
4.2.5閉水段封口不密实,又因其在井内而常被忽视,如果采用砌砖墙封堵时,应注意做好以下几点:砌堵前应把管口0.5m左右范围内的管内壁清洗干净,涂刷水泥原浆,同时把所用的砖块润湿备用;抹面应按防水的5层施工法施工;条件允许时可在检查井砌筑之前进行封砌,以利保证质量;预设排水孔应在管内底处以便排干和试验时检查。
4.2.6闭水试验是对管道施工和材料质量进行全面的检验,其间难免出现三两次不合格现象。这时应先在渗漏处一一做好记号,在排干管内水后进行认真处理。对细小的缝隙或麻面渗漏可采用水泥浆涂刷或防水涂料涂刷,较严重的应返工处理。
5检查井变形、下沉,构配件质量差
5.1产生原因
检查井变形和下沉,井盖质量和安装质量差,铁爬梯安装随意性太大,影响外观及其 使用质量。
5.2防治措施
5.2.1检查井砌筑质量应控制好井室和井口中心位置及其高度,防止井体变形。
5.2.2认真做好检查井的基层和垫层,破管做流槽的做法,防止井体下沉。
5.2.3检查井井盖与座要配套;安装时座浆要饱满;轻重型号和面底不错用,铁爬安装要控制好上、下第一步的位置,偏差不要太大,平面位置准确。
6回填土沉陷
6.1产生原因
压实机具不合适;填料质量欠佳、含水量控制不好等原因影响压实效果,给工后造成过大的沉降。
6.2预防措施
管槽回填时必须根据回填的部位和施工条件选择合适的填料和压(夯)实机具;管槽较窄时可采用微型压路机填压或人工和蛙式打夯机夯填;填料中的淤泥、树根、草皮及其腐植物既影响压实效果,又会在土中干缩、腐烂形成孔洞,这些材料均不可做为填料,以免引起沉陷;控制填料含水量大于最佳含水量2%左右;遇地下水或雨后施工必须先排干水再分层随填随压密实;杜绝带水回填或水夯法施工。
6.3处治措施
根据沉降破坏程度采取相应的措施:不影响其它构筑物的少量沉降可不做处理或只做表面处理,如沥青路面上可采取局部填补以免积水;如造成其它构筑物基础脱空破坏的,可采用泵压水泥浆填充;如造成结构破坏的应挖除不良填料,换填稳定性能好的材料,经压实后再恢复损坏的构筑物。
7结束语
城市建设离不开排水管道工程,而排水管道工程质一的优劣不仅影响城市功能的充分发挥,而且对道路完好、城市环保以及城市防洪排涝等都有直接的影晌。排水管道工程创优必须建立在主体结构工程创优的基础之上。在施工过程中要努力克服各种通病,确保整体工程施工质量达到优良。
关键词:市政排水;施工;技术措施
Abstract: The municipal sewer road construction projects although the construction process is relatively less complex, but because most of the projects are in the urban construction, the environment is complex, both underground pipelines and cables is unknown, to ensure both the safety of the works under the premise, but also consider ground transportation, and other factors, led to the increase in the difficulty of construction, construction quality and duration often can not be guaranteed. In this paper, based on the experience for many years engaged in the construction work, the municipal drainage pipe construction technology integrated analysis.Key words: municipal drainage; construction; technical measures
中圖分类号:TE832文献标识码:A 文章编号:
前言
排水管网是城市重要的基础设施,在排水系统中占有举足轻重的地位。由于历史的原因,许多城市的派水管网建设大都滞后于水厂建设,存在诸如管线老化、管径偏小或布局不合理等问题,制约了排水企业的发展。为此近年来各地都投入了大量的建设资金对市区排水管网进行改造。排水系统是其服务区内其他工程设施得以正常使用的重要设施之一,确保其施工质量至关重要。
1铺设管道前的准备工作
1.1道路的拆除与恢复
城区管道施工时,将有一定数量的既有路面被破除。为保证施工安全和路基质量,施工时要求管道在道路上开挖时,根据施工图纸设计要求,计算出开口宽度,并用白漆标注出开挖线,用切割机将路面切断,表层的破碎沥青面层及路基渣层,由挖掘机开挖,路基稳定砂层合理堆放以备回用,余土由自卸车运至弃土场。管道施工完成后,沟槽回填质量将直接影响道路的质量和使用功能。
1.2地上、地下公用设施的保护
管道沟槽开挖时,应根据地质土层情况及时采用支撑,以免造成滑坡、塌方。开挖边坡及支撑形式要交项目监理审查,得到认可后方能施工。在建筑物、构筑物基础及电线杆、灯杆附近开挖时应上报防止其下沉或变形的措施、加固工程计算书及图纸,并交项目监理审批。
某些地段需要排水,以使开挖人员始终在干燥环境中工作。排水过程不得使地面产生过大的沉降,影响现场周围的建筑物、构筑物和其他公用设施的正常使用和安全。在建筑物、构筑物基础及电线杆、灯杆附近开挖,采用钢板桩加固。在高压线下开挖时,挖掘机要求不在电线正下方工作,必要时采用人工开挖。
2管道施工
2.1沟槽开挖与支护
土方的工作量占整个工程的很大比重,在开挖前逐一探明地下既有管道、电缆和其他构筑物的位置,将调查结果和处理方案送交业主和相关管理单位确认,以便进行相应的保护、迁移等措施,保证开挖工作持续进行。
2.2管道安装
2.2.1管材的选用和检查。管材及主要配件由选定的合格制造商提供,管材进场后,由施工方材料工程师对产品的质量进行验证。当外观检查不能确保管材的质量时,进行内、外压试验。进场的管子必须是经过专业实验室批量检验合格并取得检验合格报告的产品。2.2.2下管。根据测放的中心线,用细绳控制好管道的一侧边线。采用轮胎式吊车下管,吊车沿沟槽开行至距沟边缘1 m处,以避免沟壁坍塌,影响沟槽边坡的稳定。下管时用专用吊钩或柔性吊索,严禁用钢丝绳穿入管内起吊。同时有专人指挥,绑(套)管子应找好重心,平吊轻放,避免扰动基底管道相互碰撞。管节下入沟槽时,避免与槽壁支撑及槽下的管道相互碰撞,严格控制水平与方向。管道的安装一定要符合质量要求。
3管道位置偏移或积水
3.1产生原因
测量差错,施工走样和意外的避让原有构筑物,在平面上产生位置偏移,立面上产生积水甚至倒坡现象。
3.2预防措施
3.2.1防止测量和施工造成的病害措施主要有:施工前要认真按照施工测量规范和规程进行交接桩复测与保护;施工放样要结合水文地质条件,按照埋置深度和设计要求以及有关规定放样,且必须进行复测检验其误差符合要求后才能交付施工;施工时要严格按照样桩进行,沟槽和平基要做好轴线和纵坡测量验收。3.2.2施工过程中如意外遇到构筑物须避让时,应在适当的位置增设连接井,其间以直线连通,连接井转角应大于135°。
4管道渗漏水,闭水试验不合格
4.1产生原因
基础不均匀下沉,管材及其接口施工质量差、闭水段端头封堵不严密、井体施工质量差等原因均可产生漏水现象。
4.2防治措施
4.2.1管材质量差,存在裂缝或局部砼松散,抗渗能力差,容易产生漏水。因此要求:所用管材要有质量部门提供合格证和力学试验报告等资料;管材外观质量要求表面平整无松散露骨和蜂窝麻面形象,硬物轻敲管壁其响声清脆悦耳;安装前再次逐节检查,对已发现或有质量疑问的应弃之不用或经有效处理后方可使用。
4.2.2管接口填料及施工质量差,管道在外力作用下产生破损或接口开裂。防治措施:选用质量良好的接口填料并按试验配合比和合理的施工工艺组织施工;接口缝内要洁净,对水泥类填料接口还要预先湿润,而对油性的则预先干燥后刷冷底子油,再按照施工操作规程认真施工。
4.2.3管道基础条件不良将导致管道和基础出现不均匀沉陷,一般造成局部积水,严重时会出现管道断裂或接口开裂。预防措施是:认真按设计要求施工,确保管道基础的强度和稳定性,当地基地质水文条件不良时,应进行换土改良处治,以提高基槽底部的承载力;如果槽底土壤被扰动或受水浸泡,应先挖除松软土层后和超挖部分用砂或碎石等稳定性好的材料回填密实。
4.2.4检查井施工质量差,井壁和与其连接管的结合处渗漏,预防措施:检查井砌筑砂浆要饱满,勾缝全面不遗漏;抹面前清洁和湿润表面,抹面时及时压光收浆并养护;遇有地下水时,抹面和勾缝应随砌筑及时完成,不可在回填以后再进行内抹面或内勾缝;与检查井连接的管外表面应先湿润且均匀刷一层水泥原浆,并座浆就位后再做好内外抹面,以防渗漏。
4.2.5閉水段封口不密实,又因其在井内而常被忽视,如果采用砌砖墙封堵时,应注意做好以下几点:砌堵前应把管口0.5m左右范围内的管内壁清洗干净,涂刷水泥原浆,同时把所用的砖块润湿备用;抹面应按防水的5层施工法施工;条件允许时可在检查井砌筑之前进行封砌,以利保证质量;预设排水孔应在管内底处以便排干和试验时检查。
4.2.6闭水试验是对管道施工和材料质量进行全面的检验,其间难免出现三两次不合格现象。这时应先在渗漏处一一做好记号,在排干管内水后进行认真处理。对细小的缝隙或麻面渗漏可采用水泥浆涂刷或防水涂料涂刷,较严重的应返工处理。
5检查井变形、下沉,构配件质量差
5.1产生原因
检查井变形和下沉,井盖质量和安装质量差,铁爬梯安装随意性太大,影响外观及其 使用质量。
5.2防治措施
5.2.1检查井砌筑质量应控制好井室和井口中心位置及其高度,防止井体变形。
5.2.2认真做好检查井的基层和垫层,破管做流槽的做法,防止井体下沉。
5.2.3检查井井盖与座要配套;安装时座浆要饱满;轻重型号和面底不错用,铁爬安装要控制好上、下第一步的位置,偏差不要太大,平面位置准确。
6回填土沉陷
6.1产生原因
压实机具不合适;填料质量欠佳、含水量控制不好等原因影响压实效果,给工后造成过大的沉降。
6.2预防措施
管槽回填时必须根据回填的部位和施工条件选择合适的填料和压(夯)实机具;管槽较窄时可采用微型压路机填压或人工和蛙式打夯机夯填;填料中的淤泥、树根、草皮及其腐植物既影响压实效果,又会在土中干缩、腐烂形成孔洞,这些材料均不可做为填料,以免引起沉陷;控制填料含水量大于最佳含水量2%左右;遇地下水或雨后施工必须先排干水再分层随填随压密实;杜绝带水回填或水夯法施工。
6.3处治措施
根据沉降破坏程度采取相应的措施:不影响其它构筑物的少量沉降可不做处理或只做表面处理,如沥青路面上可采取局部填补以免积水;如造成其它构筑物基础脱空破坏的,可采用泵压水泥浆填充;如造成结构破坏的应挖除不良填料,换填稳定性能好的材料,经压实后再恢复损坏的构筑物。
7结束语
城市建设离不开排水管道工程,而排水管道工程质一的优劣不仅影响城市功能的充分发挥,而且对道路完好、城市环保以及城市防洪排涝等都有直接的影晌。排水管道工程创优必须建立在主体结构工程创优的基础之上。在施工过程中要努力克服各种通病,确保整体工程施工质量达到优良。