近日,随着西气东输三线连木沁压气站1#RR机组24小时机械测试的完成,历时4天的RR机组24小时机械运转测试宣告圆满结束。连木沁压气站也成为西三线首座完成机组24小时机械测试的站场,这也标志着该站基本具备投产条件和为西三线增输的能力。机组在前期完成部件安装、单体测试、系统联合调试后,24小时测试便按部就班地展开,其目的是验证机组的机械和安装质量、
Recently, with the completion of the 24-hour mechanical test of 1 # RR unit of the third West-to-East gas pipeline, the 4-day RR unit 24-hour mechanical operation test was successfully concluded. Even the Qinqin compressor station has also become the first station on West Third Line to complete 24-hour mechanical testing of the unit, which also marks the station’s basic conditions of operation and ability to increase transmission capacity for the West Third Line. Unit completed in the pre-installation, monomer testing, joint commissioning system, 24-hour test will proceed step by step, the purpose is to verify the mechanical and installation quality of the unit,