九龙山站是北京地铁7号线与14号线换乘车站,两站同步设计、同期施工,车站东北侧出入口与商业结合,由于商业方案尚不稳定,不能与地铁同期实施,为满足地铁开通需要,与地铁相关的部分的出入口先期开工。出入口基坑施工时,地铁车站已经施工完成,商业部分的基坑型式复杂且分期施工,商业部分先期施工的基坑邻近车站一侧采用桩+锚方案,邻近后期施工一侧采用了复合土钉方案,采用GTS软件对基坑施工进行模拟,分析基坑开挖自身的受力情况,以及对地铁车站的影响。根据分析结果针对性地采取措施,将变形控制在允许范围内,对同类工程具有一定的借鉴意义。
Jiulongshan Station is a transfer station for Beijing Metro Line 7 and Line 14, with simultaneous design of the two stations and simultaneous construction. The entrance and exit on the northeast side of the station are integrated with commerce. Since the commercial scheme is not stable and can not be implemented in parallel with the MTR, Needed, the entrances and exits to the subway-related parts were started earlier. At the construction of entrance and exit excavation, the construction of subway station has been completed. The type of foundation pit in commercial part is complicated and the construction is carried out in phases. The pile and anchor plan is adopted on the adjacent station side of the foundation pit for commercial construction in advance, and the composite soil nailing Program, the use of GTS software to simulate the construction of the pit, excavation excavation of their own force situation, as well as the impact of the subway station. According to the results of the analysis, the measures are taken in a targeted manner and the deformation is controlled within the allowable range, which is of some reference to similar projects.