梨树塔隧道为分离式黄土隧道,于2013年6月1日在K18+558掌子面位置发生塌方,湿软黄土大量涌出,初支变形严重,侵入净空最大达35cm,,二衬出现裂缝,局部出现塌坑,严重影响到隧道施工安全及施工进度。针对该隧道病害的特征、形成原因进行分析及处治方案比选,最终确定采用地表旋喷桩加固综合治理方案,监控量测数据表明:围岩强度及稳定性明显改善,隧道收敛变形得到有效控制,施工进度明显加快,取得了良好的治理效果,为今后类似土质隧道病害治理提供了借鉴。
The Lishuita Tunnel is a separate loess tunnel. On June 1, 2013, landslides occurred on the face of K18 + 558 face. A large amount of wet soft loess erupted. The deformation of the initial branch was serious and the maximum intruded clearance reached 35cm. The second lining appeared Cracks, partial collapse pit, a serious impact on the tunnel construction safety and construction progress. In view of the characteristics of the tunnel disease, the formation of the reasons for the analysis and treatment options comparison, and ultimately determine the use of surface jet grouting reinforcement comprehensive control program, monitoring measurement data show that: the surrounding rock strength and stability improved significantly, the tunnel convergence and deformation are effectively controlled , The construction progress obviously accelerated, and achieved a good governance effect for the future similar soil tunnel disease control provides a reference.