论文部分内容阅读
天津工程机械研究所对装载机传动系随机载荷的研究已有五、六年的历史,先后作过三次装载机现场作业测试,测取了大量随机载荷数据。工程机械传动系载荷比较复杂,包括各部件的转速、扭矩、功率、压力等。试验数据用模拟磁带记录,直接测量参数和派生参数约20个,参数多,数据量大,一般计算机是无法承担其处理工作的。开始曾用 C—120、F—120、仪器加手工
Tianjin Research Institute of Construction Machinery loaders drive train random load research has been five or six years of history, has done three loader job site test, measured a large number of random load data. Construction machinery transmission system load is more complicated, including the speed of each component, torque, power, pressure and so on. Test data recorded using analog tape, direct measurement of parameters and derived parameters of about 20, the parameters of large amount of data, the general computer can not afford to deal with its work. Started using C-120, F-120, equipment and manual