只要有担当的精神,办法总比困难多。从汶川到重庆,从安置房到金融街融景中心项目,陈军一直践行着这一理念。“2009年7月,中建二局三公司项目经理陈军带领一支22人的分队从什邡援建前线来到了汶川,在这个物资极其匮乏的重灾区,他们在不到6个月时间里令人难以置信地建起了汶川县最高的标志性建筑—住房安置小区三期工程三座塔式楼,优质高效地创下了三天半一个结构层的施工奇迹,
As long as there is a responsible spirit, there are always more ways than difficulties. From Wenchuan to Chongqing, from the resettlement room to the Financial Street Rongjing Center project, Chen Jun has been practicing this philosophy. ”In July 2009, Chen Jun, project manager of the Third Company of China Construction Second Bureau, led a 22-unit team from Shifang to build the front line to Wenchuan. In less than 6 months in this extremely scarce area where supplies were extremely scarce, Incredibly built in Wenchuan County, the tallest landmark - Housing Resettlement Area Phase III of three towers, high-quality and efficient set a three days and a half of the construction layer of a miracle,