山东济南顺河高架路北延工程,全线采用高架桥形式,上部结构为钢筋混凝土连续箱梁。其中第二合同段全长1038米(K0+139- K1+577),由中铁三局二公司济南顺河高架路北延工程项目部承包施工。等宽段桥面24.5米,长750 米,上部结构为预应力混凝土连续梁;收费站,长288米为18孔16米钢筋混凝土连续箱梁。下部结构
Shandong Jinan Shun Ho viaduct north extension project, all over the viaduct form, the upper structure of reinforced concrete continuous box girder. The second contract section of which is 1038 meters in length (K0 + 139- K1 + 577) is contracted and constructed by the project of Northward Extension Project of Jinan Shunhe Elevated Road, Jinan Railway Third Bureau. The equivalent width of bridge deck 24.5 meters, 750 meters long, the upper structure of prestressed concrete continuous beams; toll stations, 288 meters long 18 holes 16 meters of reinforced concrete continuous box girder. The lower structure