电子工业部能源办公室于今年5月29日至6月1日在四川宜宾七九九厂召开了窑炉余热利用现场会议,参加会议的有部属有关工厂并邀请部分兄弟部及省市有关部门代表共78人。七九九厂是一个个以生产电子陶瓷元件为主的工厂,近两年多来在该厂5台隧道式窑炉的冷却带加装34台余热蒸汽锅炉和4台余热热水锅炉,又利用烟气余热建成了一
The Energy Office of the Ministry of Electronics Industry held an on-site meeting on kiln waste heat utilization at Yibin 799 Plant of Sichuan Province from May 29 to June 1 this year. Some of the participating factories attended the meeting and invited some brothers and ministries and representatives from relevant departments of provinces and cities A total of 78 people. Seven nine nine factory is a production of electronic ceramic components based factory, nearly two years in the plant five tunnel kiln cooling belt installed 34 sets of waste heat steam boiler and 4 sets of waste heat boiler, and Built using flue gas heat one