论文部分内容阅读
宝钢总厂的建设为全国人民所关心,目前一期工程已基本完成,正临投产前夕,兹趁上海市金属学会复会六周年,《上海金属》创刊五周年纪念之际,将建设及装备概况作一简单的汇报。一、概况宝钢的总体规划以两座4000M~3级高炉为中心,从原料码头开始,包括料场、焦化、烧结、炼钢、连铸、初轧开坯、热连轧板机、冷连轧板机、连轧管机到成品码头为止,以及相应的公用、辅助设施。一期工程以一号
The construction of Baosteel Plant is of concern to people across the country. At present, the first phase of the project has basically been completed. On the eve of its commissioning, the 6th Anniversary of the Resumption of Shanghai Society of Metals and the 5th Anniversary of the Founding of Shanghai Metal will be built and equipped Profile for a simple report. I. Overview The overall planning of Baosteel focuses on two 4000M ~ 3 blast furnaces, starting from raw material terminals, including stockyard, coking, sintering, steel making, continuous casting, bloom rolling, hot rolling mill, cold rolling Rolling mill, rolling mill to the finished product terminal, and the corresponding public, auxiliary facilities. A project to number one