我单位在阿克苏水泥厂物料库圆形漏斗钢筋混凝土工程施工中,采用了悬空土模施工方法,既节约了时间,又节省了材料。水泥厂物料库在筒仓高4.6m 处,有一现浇钢筋混凝土漏斗呈圆锥形,壁厚15cm,双层布筋,排列4个,同时施工。如果用定型钢模或木模均费时、费料。鉴于这种情况,我们就地取材,采
My unit in the Aksu cement factory materials warehouse circular funnel reinforced concrete construction, the use of suspended earth mode construction method, which saves time and saves material. Cement material warehouse in the silo 4.6m high, there is a cast-in-place reinforced concrete funnel conical, wall thickness 15cm, double cloth reinforcement, arranged in four, at the same time construction. If you use stereotypes die or wood mold are time-consuming, fee. In view of this situation, we draw on the spot, mining