利用静压力将予制桩逐段压入土中是一种新的沉桩工艺。武汉市于1977年研制了一台YC—60液压静力压桩机,这台压桩机可以克服压桩施工中最大动阻力60吨。自1977年以来,先后在住宅、工业厂房、烟囱基础、剧院等十二项工程进行了压桩施工,总共压工程桩近2500根,试验桩18根。桩的入土深度最深为27.4米,最浅为3米。大部分桩为14米至20米。予制桩段长度有3米、4米、6米三种。单桩允许承载力为25吨至50吨。通过压桩施工和桩的静载荷试验表明,在武汉地区采用压桩施工处理软土地基具有施工文明,质量可靠,技
The use of static pressure to press pre-pile into the soil segment by segment is a new sinking process. In 1977, Wuhan City developed a YC-60 hydraulic static pile driver, which can overcome the maximum dynamic resistance of 60 tons in the construction of the pile. Since 1977, a total of 12 projects, including residential buildings, industrial plants, chimney foundations, and theaters, have been piled on piles, and a total of nearly 2,500 piles have been pressed and 18 piles have been tested. The deepest depth of the pile is 27.4 meters and the shallowest is 3 meters. Most of the piles are 14 to 20 meters. The length of the precast section is three meters, four meters and six meters. Single piles allow a bearing capacity of 25 tons to 50 tons. Through the pile-pressing construction and the static load test of the pile, it is shown that the construction of the soft soil foundation using the pile-pressing construction in the Wuhan area has the construction civilization, and the quality is reliable.