国内高炉采用汽化冷却以100米~3高炉效果最好。我厂3号100米~3高炉汽化冷却是在1980年12月大修改造后投产的,至今仍在正常运行。一、汽化冷却结构特征1.热负荷确定改造前高炉系喷水冷却,热负荷不易测定。本次设计参考了同类型企业阳泉、济铁、信阳三个厂100米~3高炉测定数据,结合我厂自焙炭砖内衬导热性良好的特点,确定炉
Domestic blast furnace using evaporative cooling to 100 m ~ 3 blast furnace best. I plant on the 3rd 100 meters ~ 3 blast furnace gasification cooling is in December 1980 after the overhaul and put into operation, is still in normal operation. First, the characteristics of vaporization cooling 1. Heat load to determine the transformation of the blast furnace water spray cooling, heat load is not easy to measure. The design reference to the same type of enterprises Yangquan, Jinan Iron and Steel, Xinyang three plants 100 meters ~ 3 blast furnace measured data, combined with our factory self-baking charcoal brick lined with good thermal conductivity, determine the furnace