1997年10月22日至23日由国家电力公司主持对葛洲坝二江电厂实现“无人值班”(少人值守)进行验收。验收组在听取了自查情况汇报后,深入现场,对照部颁规定,就设备运行状况,人员素质,管理制度等进行了认真检查。认为葛洲坝二江电厂主、辅设备运行稳定,人员素质较高,规章制度完善,对照电安生【1996】484号文“关于颁发《水电厂”无人值班“(少人值守)的若干规定》(试行)的通知”的三个基本条件,符合“无人值班”(少人值守)要求,验收合格。至此,葛洲坝二江电厂成为
From October 22 to October 23, 1997, the State Power Corporation presided over the acceptance of the “Unattended” (less-person duty) implementation of Gezhouba Erjiang Power Plant. After receiving the self-inspection report, the acceptance team went deep into the site and compared with the regulations issued by the ministry. They carefully checked the equipment operation status, personnel quality, and management system. It is believed that the operation of the main and auxiliary facilities of the Gezhouba Erjiang Power Plant is stable, the personnel quality is high, and the rules and regulations are perfect. In contrast to the “Anhui Electrician” [1996] No. 484 article, “About the issuance of “hydropower plants” and “unattended” (less people on duty) The three basic conditions for the “Regulations” (Trial) notification are in accordance with the requirements of “Unattended” (less-person duty) and acceptance. At this point, Gezhouba Erjiang Power Plant became