为了节约钢材,解决钢板供应的困难和便于就地制造,武义县沅口水库溢洪闸,把原设计的3扇钢闸门改为钢丝网水泥弧形闸门,从76年2季度工地自行浇制后,由于“四人邦”的干扰和破坏,铸钢件的浇铸和金加工工作拖延了一年多时间在英明领袖华主席一举粉碎“四人邦”后,提出抓纲治国的战略决策的大好形势下,在金华地区机械施工大队支援下,于今年初开始按装启闭机和闸门,到6月9日全部完成,并于10日试运动,情况良好,现已关闸投入运行。该闸门尺寸为7米×5.5米(宽×高)最大工作水头11.8米,为潜孔式,闸门各部件中
In order to save steel, to solve the difficulties of steel supply and ease of manufacturing in situ, Wuyi County, Yuankou reservoir spillway floodgate, the original design of the three steel gate into the steel mesh arc gate, from the second quarter of 76 site pouring After the “gang of four,” the interference and sabotage cast steel casting and gold processing delayed more than a year after wise leader leader hua in one fell swoop smash the “gang of four,” put forward the strategic decision to rule the country Under the excellent situation, with the support of the construction team of Jinhua Machinery Company, the hoist and gate were installed at the beginning of this year and all were completed on June 9, and the trial run on the 10th was in good condition. The barrier gate has now been put into operation. The gate size of 7 m × 5.5 m (W × H) maximum working head of 11.8 meters, for the DTH, each part of the gate