某大型钢铁厂废水处理回用工程在原有工艺基础上提标改造,增加深度处理,进水为生产废水和生活污水按9∶1混合水,处理水量为2 000 m~3/h,预处理工艺为格栅、调节池、高密度沉淀池、V型滤池,深度处理采用浸没式超滤、反渗透系统,系统出水水质满足钢铁厂回用水标准。其中将浸没式超滤作为反渗透进水的前处理工艺,超滤出水水质稳定,完全满足反渗透进水要求,浊度<1 NTU,SDI<3,运行成本低。
A large iron and steel plant wastewater treatment and reuse project based on the original process of upgrading the standard to increase the depth of treatment, water for the production of waste water and domestic sewage mixed water by 9: 1, the treated water volume of 2 000 m ~ 3 / h, pretreatment Process for the grille, regulating pool, high-density sedimentation tanks, V-type filter, depth treatment using submerged ultrafiltration, reverse osmosis system, the system effluent quality to meet the water reuse standards of steel mills. Among them, immersion ultrafiltration is used as the pretreatment technology for reverse osmosis water inflow. The quality of ultrafiltrated effluent is stable and fully meets the requirements of reverse osmosis infiltration. The turbidity <1 NTU, SDI <3, low operating cost.