在国际工程项目工期索赔中,由于受多因素影响,工期索赔责任归属难以判别和责任比例难以测定,现有单一方法不能完全解决问题,因此在已有的国际工程项目工期索赔计算方法研究成果的基础上,通过比较现有的几种计算方法,并进行适当改进,探索出一种更合理的工期索赔定量化计算方法,即通过韦恩图将共同延误进行分解,进而对多因素影响下的国际工程项目工期延误责任进行较为精确合理的划分。
In the claim of the international project, due to the influence of many factors, it is difficult to determine the attribution of the liability for the construction period and the determination of the proportion of the liability. The existing single method can not completely solve the problem. Therefore, in the existing research results of the claim calculation method of the international project period Based on the comparison of several existing calculation methods and the appropriate improvement, a more reasonable method for calculating the calculation of the duration claims is proposed, that is, the common delays are decomposed by means of Wayne diagram, and then the multi-factors International project project liability for a more precise and reasonable delay.