南昌地铁1号线5标段盾构隧道穿越抚河,抚河下有破除桥梁残留的临时钢筋混凝土桩等障碍物。采用地质雷达确定了抚河段内未知地下障碍物的位置,同时对盾构机刀盘配制、螺旋输送机和掘进参数进行了分析。研究表明:为了保证盾构机安全穿越地下障碍物区,刀盘刀具需具备一定的破岩能力,同时需对刀盘转速和掘进速度进行控制;最后分析了穿越地下障碍物对盾构机的影响。这对今后地铁盾构隧道工程有一定的指导意义。
Nanchang Subway Line 1 5 section shield tunnel through the Fu River, Fu River under the bridge to remove the temporary reinforced concrete piles and other obstructions. Geological radar was used to determine the location of unknown underground obstacles in the Fushui section. At the same time, the preparation of shield cutter, screw conveyor and driving parameters were analyzed. The research shows that in order to ensure the safety of shield tunneling through the underground obstacle area, the cutting tool must have certain rock breaking ability, meanwhile it needs to control the speed of cutter head and the driving speed. At last, influences. This has certain guiding significance for the future subway shield tunnel project.