论文部分内容阅读
摘要:本文详细介绍了蓄水预压法在等截面连续梁支架预压施工中的应用,阐述了该技术的施工工艺流程、支架预压控制要点,与其它堆载预压方法相比,具有省时、省力、经济实用、施工方便等优点。
关键词:蓄水;预压;等截面;连续梁;沉降观测
Abstract: this paper introduces the water storage preloading method such as continuous beam section in support of the application of the preloading construction, this paper discusses the technology of construction process flow, stents preloading control points, and other preloading method, it is characterized by the save time, energy, and economic and practical, construction is convenient, etc.
Keywords: water storage; Preloading; Uniform; Continuous beam; Settlement observation
中图分类号: [TU196.2] 文献标识码:A 文章编号:
一、前言
等截面现浇预应力连续梁的施工在钢筋安装、混凝土浇筑前进行支架预压是十分必要的,在确保施工质量和安全的前提下,支架预压方法的选择将对施工工期、工程施工成本产生深远的影响。本人通过多座现浇连续梁桥的施工,经与其它预压法比较,认为蓄水预压法是一种经济、实用、施工方便、高效的施工预压办法。
二、工程概况
南通路东升桥桥跨布置为13m+13m+13m预应力等截面连续梁,整体现浇。全桥按两幅布置,中间留2cm空隙,单幅梁底宽18m,两侧悬臂长1m,梁高0.7m,中横梁宽2m,端横梁宽1m,梁体在中横梁及端横梁之间范围内采用布置圆形孔道的方式进行局部挖空,孔道直径为40cm。
三、支架蓄水预压法施工工艺
支架搭设→底模铺设→蓄水土袋围堰堆筑或支立侧模→铺设双层塑料布→沉降观测点设置→蓄水加载→沉降稳定→排水卸载→下道工序施工。
四、支架预压荷载及范围
本次预压范围为北幅桥,北幅桥长38.92m,宽20m,高0.7m。按照设计和施工规范要求,支架搭设、底模铺设完成后,要对支架进行预压,预压重量不小于1.2倍的连续板自重。
北幅桥连续板自重:
V砼=﹝18×0.7+0.5×(0.2+0.3)×1+0.5×(0.2+0.3)×0.99﹞×38.92-(1.321×17×2+1.351×17)
=441.874m3
取钢筋混凝土的容重=2.50t/m3
则预压重量为:1.2×2.50×441.874=1325.622t
水压高度H水==1.703m(取水的密度为1.0t/ m3)
五、预压方法
本工程预压拟采用全断面水压法,由于施工现场没有1.7m高的模板,采用土袋在北幅桥底模四周堆成1.7m高的围堰,由于灌水时侧压力较大,必须确保土袋围堰的稳定,必要时用木板、钢管支撑土袋围堰。围堰内底模上内贴彩色塑料布两层,塑料布搭接采用万能胶和胶布粘贴,塑料布一直铺到土袋围堰顶上,采用水压,防止漏水至关重要,为保险起见在上荷载之前多做试验,确保塑料布接缝处不漏水。蓄水预压示意图见下图:
六、预压时间
预压时间以储满水算起,预压期为7d。预压采用2台15KW的污水泵向围堰内抽水,并保持围堰内水位保持在1.7m。
预压采用分级均匀加载,共分四级,每次注水高度为0.425m。
七、沉降观测
沉降观测是一道重要的程序,是准确评价支架的性能是否满足施工要求。支架预压的结果要通过沉降观测得出,仪器采用专用精密水准仪。
1、测点布置
为了解支架沉降情况,在加水预压进行之前测出各测量控制点标高,测量控制点用红漆做出标志,测量控制点按顺桥向布置。变形观测点布置点见下图:
2、观测阶段
观测分成六个阶段:预压加载前、25%荷载、50%荷载、75%荷载、100%荷载、卸载后。每个观测阶段要观测2次。测量观测每天安排一次,持载后观察三天,若连续三天观测数据变化在1mm以内则可卸载,卸载后继续观测一天。
3、观测要点
测量前认真校验水准仪,测量时前后视距尽量相等,每次测量最好在同一位置架设仪器,一个测站测完。
4、观测成果
沉降观测数据如实填写在沉降观测记录上,计算出支架弹性变形值和非弹性变形值,以便调整底模標高。
八、水压法预压应注意的事项
①、蓄水预压时,对土袋围堰(模板)的侧压力较大,为确保水压法预压的正常进行,加设支撑。
②、在加水前对支架上铺设的蓄水材料仔细检查,以防止漏水造成模板的变形。
③、蓄水前做好安全防护工作,蓄水后严禁闲杂人员进入预压区。
九、蓄水预压法的优点分析
通过支架蓄水预压法在本桥现浇等截面砼连续梁中的应用,与其它堆载预压法相比,该方法有以下优点:
1、施工工效:采用蓄水预压法一般6~8h能够达到要求的荷载,3~5h可完成卸载,比其它堆载预压法节约工期4~6天,这对加快工程施工进度非常有利。
2、加载的均匀性:蓄水预压的加载过程可视为匀速加载,且荷载分布均匀,对支架系统的安全较为有利。若采用其它堆载预压法,存在荷载及布载不均匀的情况,支架存在因受力不均匀可能引起局部沉降过大,导致支架整体失稳。
3、环境影响方面:蓄水预压直接采用河水或井水,无污染,不会对周边环境造成很大的影响,施工现场较为干净整洁,有利于环境保护和文明施工。其它堆载预压法需要大量的黄砂或泥土,无疑会对周边环境产生影响,不利于现场文明施工和安全生产。
4、工程成本:蓄水预压所用的支撑材料、塑料布可以重复利用,且只需投入少量的人工,工效很高;而其它堆载预压法需要大量的人工、吊车,材料浪费也很严重,施工时间较长,经估算采用蓄水预压法与其它堆载预压法相比可以节约一大半成本。
5、沉降观测:蓄水预压沉降观测可以直接在支架底模顶面取点,方便检测,而其它堆载预压上面取点困难,不利于沉降观测的准确掌握。
6、卸载:蓄水预压法卸载方便,只需用污水泵将水抽出即可,无需大量的人力或机械设备。
十、结语
对等截面混凝土现浇连续梁支架采用蓄水法进行预压,比其它堆载预压提高了劳动效率,对于桥梁宽度比较大、预压孔数比较多的连续梁节省了大量的劳动力,加快了桥梁工程施工进度。
参考文献
[1]、周水兴、何兆益.《路桥施工计算手册》.人民交通出版社.2004
[2]、邵旭东主编.《桥梁工程》.武汉理工大学出版社.2004
关键词:蓄水;预压;等截面;连续梁;沉降观测
Abstract: this paper introduces the water storage preloading method such as continuous beam section in support of the application of the preloading construction, this paper discusses the technology of construction process flow, stents preloading control points, and other preloading method, it is characterized by the save time, energy, and economic and practical, construction is convenient, etc.
Keywords: water storage; Preloading; Uniform; Continuous beam; Settlement observation
中图分类号: [TU196.2] 文献标识码:A 文章编号:
一、前言
等截面现浇预应力连续梁的施工在钢筋安装、混凝土浇筑前进行支架预压是十分必要的,在确保施工质量和安全的前提下,支架预压方法的选择将对施工工期、工程施工成本产生深远的影响。本人通过多座现浇连续梁桥的施工,经与其它预压法比较,认为蓄水预压法是一种经济、实用、施工方便、高效的施工预压办法。
二、工程概况
南通路东升桥桥跨布置为13m+13m+13m预应力等截面连续梁,整体现浇。全桥按两幅布置,中间留2cm空隙,单幅梁底宽18m,两侧悬臂长1m,梁高0.7m,中横梁宽2m,端横梁宽1m,梁体在中横梁及端横梁之间范围内采用布置圆形孔道的方式进行局部挖空,孔道直径为40cm。
三、支架蓄水预压法施工工艺
支架搭设→底模铺设→蓄水土袋围堰堆筑或支立侧模→铺设双层塑料布→沉降观测点设置→蓄水加载→沉降稳定→排水卸载→下道工序施工。
四、支架预压荷载及范围
本次预压范围为北幅桥,北幅桥长38.92m,宽20m,高0.7m。按照设计和施工规范要求,支架搭设、底模铺设完成后,要对支架进行预压,预压重量不小于1.2倍的连续板自重。
北幅桥连续板自重:
V砼=﹝18×0.7+0.5×(0.2+0.3)×1+0.5×(0.2+0.3)×0.99﹞×38.92-(1.321×17×2+1.351×17)
=441.874m3
取钢筋混凝土的容重=2.50t/m3
则预压重量为:1.2×2.50×441.874=1325.622t
水压高度H水==1.703m(取水的密度为1.0t/ m3)
五、预压方法
本工程预压拟采用全断面水压法,由于施工现场没有1.7m高的模板,采用土袋在北幅桥底模四周堆成1.7m高的围堰,由于灌水时侧压力较大,必须确保土袋围堰的稳定,必要时用木板、钢管支撑土袋围堰。围堰内底模上内贴彩色塑料布两层,塑料布搭接采用万能胶和胶布粘贴,塑料布一直铺到土袋围堰顶上,采用水压,防止漏水至关重要,为保险起见在上荷载之前多做试验,确保塑料布接缝处不漏水。蓄水预压示意图见下图:
六、预压时间
预压时间以储满水算起,预压期为7d。预压采用2台15KW的污水泵向围堰内抽水,并保持围堰内水位保持在1.7m。
预压采用分级均匀加载,共分四级,每次注水高度为0.425m。
七、沉降观测
沉降观测是一道重要的程序,是准确评价支架的性能是否满足施工要求。支架预压的结果要通过沉降观测得出,仪器采用专用精密水准仪。
1、测点布置
为了解支架沉降情况,在加水预压进行之前测出各测量控制点标高,测量控制点用红漆做出标志,测量控制点按顺桥向布置。变形观测点布置点见下图:
2、观测阶段
观测分成六个阶段:预压加载前、25%荷载、50%荷载、75%荷载、100%荷载、卸载后。每个观测阶段要观测2次。测量观测每天安排一次,持载后观察三天,若连续三天观测数据变化在1mm以内则可卸载,卸载后继续观测一天。
3、观测要点
测量前认真校验水准仪,测量时前后视距尽量相等,每次测量最好在同一位置架设仪器,一个测站测完。
4、观测成果
沉降观测数据如实填写在沉降观测记录上,计算出支架弹性变形值和非弹性变形值,以便调整底模標高。
八、水压法预压应注意的事项
①、蓄水预压时,对土袋围堰(模板)的侧压力较大,为确保水压法预压的正常进行,加设支撑。
②、在加水前对支架上铺设的蓄水材料仔细检查,以防止漏水造成模板的变形。
③、蓄水前做好安全防护工作,蓄水后严禁闲杂人员进入预压区。
九、蓄水预压法的优点分析
通过支架蓄水预压法在本桥现浇等截面砼连续梁中的应用,与其它堆载预压法相比,该方法有以下优点:
1、施工工效:采用蓄水预压法一般6~8h能够达到要求的荷载,3~5h可完成卸载,比其它堆载预压法节约工期4~6天,这对加快工程施工进度非常有利。
2、加载的均匀性:蓄水预压的加载过程可视为匀速加载,且荷载分布均匀,对支架系统的安全较为有利。若采用其它堆载预压法,存在荷载及布载不均匀的情况,支架存在因受力不均匀可能引起局部沉降过大,导致支架整体失稳。
3、环境影响方面:蓄水预压直接采用河水或井水,无污染,不会对周边环境造成很大的影响,施工现场较为干净整洁,有利于环境保护和文明施工。其它堆载预压法需要大量的黄砂或泥土,无疑会对周边环境产生影响,不利于现场文明施工和安全生产。
4、工程成本:蓄水预压所用的支撑材料、塑料布可以重复利用,且只需投入少量的人工,工效很高;而其它堆载预压法需要大量的人工、吊车,材料浪费也很严重,施工时间较长,经估算采用蓄水预压法与其它堆载预压法相比可以节约一大半成本。
5、沉降观测:蓄水预压沉降观测可以直接在支架底模顶面取点,方便检测,而其它堆载预压上面取点困难,不利于沉降观测的准确掌握。
6、卸载:蓄水预压法卸载方便,只需用污水泵将水抽出即可,无需大量的人力或机械设备。
十、结语
对等截面混凝土现浇连续梁支架采用蓄水法进行预压,比其它堆载预压提高了劳动效率,对于桥梁宽度比较大、预压孔数比较多的连续梁节省了大量的劳动力,加快了桥梁工程施工进度。