经过3年的紧张施工,2011年6月上海市“十一五”重大工程,长江青草沙原水系统工程全面建成通水,按原定计划上海各自来水厂分成四个时间节点,实施了通水切换的目标。从2010年12月1日浦东新建成的金海水厂实现了第一批通水切换,到201 1年6月最后一批的长桥、凌桥2座水厂相继进行了切换通水,从而使上海市各行政区渝1000万人口率先受益用上了青草沙优质长江水,改写了上海饮用水主要依靠黄浦江水源的历史和格局,通过这次优
After three years of intense construction, the “Eleventh Five-Year” major project of Shanghai Municipality in June 2011 and the Changjiang Qingcaosha Sediment Water System Project have been fully completed and opened to water. According to the original plan, the respective water plants in Shanghai are divided into four time nodes and implemented The goal of switching water. From December 1, 2010 Pudong new Jinhai water plant to achieve the first batch of water switching, to June 2011 the last batch of Longbridge, Lingqiao two water plants have been switched to water, which Make Shanghai 10 million people in all districts of Yu first take advantage of the quality of the Yangtze River water Qingcaosha, rewriting the history of Shanghai drinking water relies mainly on the Huangpu River water source and the pattern through this excellent