南京长江第四大桥北塔基础采用高桩承台结构,桩基直径大、深度深,且穿过近50m的砂质泥岩层,钻进和成孔难度大,哑铃形钢吊箱围堰的制造安装复杂。针对工程施工难点,介绍了南京长江第四大桥北塔施工平台搭设、大直径砂质泥岩带浆钻进、哑铃形大平面尺寸钢吊箱围堰的加工制造等关键施工技术,并对钢吊箱围堰的整体吊装下放、精确定位及封底施工进行了研究。实践结果表明,北塔基础工程质量符合国家规范和设计要求。
The North Tower of the Fourth Nanjing Yangtze River Bridge uses a high-pile cap structure with large pile diameter and deep depth. It is difficult to drill and form holes through the sandy mudstone layers of nearly 50m. The ductile steel cofferdam cofferdam Manufacturing and installation complex. In view of the difficulties in construction, the key construction technologies such as erection of the North Tower of the Fourth Bridge of the Nanjing Yangtze River Delta, drilling of large-diameter sandy mudstone and steel cofferdam of dumbbell-shaped large flat steel cage are introduced. The overall cofferdam coffering is decentralized, the precise positioning and back cover construction are studied. Practice shows that the quality of the basic project of North Tower conforms to the national norms and design requirements.