由贵州省普定水电站工程指挥部主持于1995年10月26至27日在贵州省红枫水力发电总厂召开了普定水电站水情自动测报系统验收会。贵州省电力局、乌江开发公司、贵州省无线电管理委员会、红枫发电总厂、贵阳勘测设计院、贵州省水文总站、乌江渡水电厂、东风发电厂等十几个单位四十余名专家代表出席了会议。会议对系统中心站和部分测站进行了现场功能观摩检测,听取了项目组的研制总结及用户对系统运行考核的总结报告等,对提交会议的技术资料进行了审查,会议认为该系统各项技术指标均已达到设计任务书和有关规范要求,一致同意能通过验收移交。
Puding Hydropower Station project headquarters in Guizhou Province presided over October 26, 1995 27 to 27 in Guizhou Hongfeng Hydropower Plant Puding Hydropower Station hydrological automatic reporting system acceptance. Guizhou Power Authority, Wujiang Development Company, Guizhou Province Radio Management Committee, Hongfeng Power Plant, Guiyang Survey and Design Institute, Guizhou Provincial Hydrological Station, Wujiangdu Hydropower Station, Dongfeng Power Plant, a dozen units more than 40 experts Attended the meeting Meeting on the system central station and some stations on-site functional observation test, listened to the project team summary and user evaluation of the system summary report, etc., to submit the technical information submitted to the meeting was reviewed, the meeting that the system Technical indicators have reached the design task book and the relevant regulatory requirements, agreed to pass the acceptance transfer.