鹿角坝水库的成库方式是把地层中存在岩溶渗漏管道通过特殊工艺的灌浆技术改造为(“大坝”)工程岩体,最大限度地发挥地质体的工程作用,使其具备安全性高,运行、维护成本低之特色。根据鹿角坝岩溶封堵处理方案的具体实施情况,总结贵州喀斯特地貌溶蚀发育区溶洞的处理方法,以便对今后的无坝水库的处理施工有一定的借鉴意义。
The way of reservoir formation of Lukaku dam is to transform the grouting technology of karst seepage pipeline in the stratum into “(” “dam”) engineering rock by special technology to maximize the engineering effect of geologic body and make it safe High sex, running, low maintenance costs. According to the actual implementation of the karst blockage treatment scheme in Lukaku dam, the treatment methods of karst caves in the karst area of karst physiognomy in Guizhou are summarized so as to provide reference for future treatment and construction of No-dam reservoirs.