为了更准确地计算工期变更后的费用增减,拟采用关键线路法(CPM)和计划评审技术(PERT)对合同投标文件的网络计划进行分析,计算非承包商原因造成的工期延误时间,得到实际有效工期。根据收集的工期、投标报价、实际结算以及进度数据,利用数学模型技术(MMT)建立他们之间的模型关系并检验,若该模型成立,则计算出的费用即为非承包商原因造成的工期延误索赔费用。这种量化的计算方法更具科学性,可以减少合同双方争议,可供工程实际参考。
In order to more accurately calculate the change of costs after the change of schedule, it is proposed to analyze the network plan of contract bidding documents by key line method (CPM) and plan evaluation technology (PERT) to calculate the time delay caused by non-contractors and obtain the The actual effective duration. Based on the collected project duration, bid quotation, actual settlement and progress data, mathematical models (MMT) are used to establish the model relationship between them and test. If the model is established, the calculated costs are the durations due to non-contractors Delays in claim costs. This quantitative calculation method is more scientific, can reduce the controversy between the two sides of the contract, for engineering reference.