102国道长春境内段全长158.1km,其中公路里程135.7km,是贯穿我市南北的主骨架公路。根据交通部1989年印发的《关于102国道实施GBM工程的通知》精神,我市在1990年初,就着手制定了102国道工程的实施计划。1990~1991年共投资400万元,先后完成了长春郊区、榆树、德惠部分路段40.2km的GBM工程,并积累和摸索了一定的实践经验。1992年投资1300万元,对102国道长春境内段剩余的95.5km全面实施了GBM工程。在省、市、县各级主管部门的支持下,经广大职工的奋发努力,大干120天,1992年8月20日全面完成
National Highway 102 Changchun territory of the total length of 158.1km, of which 135.7km highway mileage, is running through the city’s main north-south highway. According to the “Notice on the Implementation of GBM Engineering of State Road 102” promulgated by the Ministry of Communications in 1989, the city started the implementation plan of the State Highway 102 in early 1990. From 1990 to 1991, a total investment of 4000000 yuan, has completed the suburbs of Changchun, Elm, Dehui part of the road 40.2km GBM project, and accumulated and groping a certain amount of practical experience. In 1992, it invested 13 million yuan to fully implement the GBM project on the remaining 95.5km of the section of Changchun in the No.102 National Highway. With the support of the competent departments at all levels of the province, city and county, and with the hard work of the vast numbers of staff and workers, they have worked hard for 120 days and completed on August 20, 1992