论文部分内容阅读
用振动放矿的阶段强制崩落法开采硬岩厚矿床时,采用在中间水平用运输机出矿和下部水平用电机车运矿的集中水平工艺流程,是有发展前途的流程之一。由于二次破碎、处理卡斗和转运巷道集矿作业与电机车运输作业无关,故这种工艺流程可在空间上使装矿与放矿分开,而在工艺上使两者互不干扰。西伯利亚矿业生产联合公司各矿采用运输机运矿的工艺流程,可以简化各水平的采准和减少掘进工程量8~15%;将运搬水平和运输水平分开,可为放矿和运搬系统的遥控以及电机车运输系统的自动控制创造先决条件。
It is one of the promising processes for the exploitation of hard-rock thick deposits by the forced caving method in the stage of vibratory ore caving using a centralized horizontal process flow of transporting ore at the intermediate level with a conveyor and transporting the ore with a lower level. Due to the secondary crushing, handling of caravans and the transportation of roadway ore gathering operations have nothing to do with the transport of electric locomotives, so this process can make the separation of ore loading and ore separation in the space, but in the process so that the two do not interfere with each other. The Siberian Mining Production Joint Company’s mines use transport aircraft to transport mined ore, which can simplify the approval of all levels and reduce the amount of excavation work by 8-15%. Separating the transport level and transport level can be used for ore handling and transportation systems Remote control and electric car transport system to create automatic control of the prerequisites.