1 工程概况某小学办公楼,为五层砖混结构,长51m、宽11.5m、层高3.3m、总建筑面积为3053m~2,横墙承重,楼盖为预制空心板。基础构造为灰土垫层上做条形基础,埋深1.3m。该工程在竣工验收前后发现东山墙窗台下产生水平裂缝,最大缝宽达7mm,在底层靠近东山墙的纵墙端部有上宽下窄的斜缝,最大缝宽3mm。事故发生以后,施工单位会同设计单位及检测部门马上对工程进行测定并记录沉降和裂缝的发展情况。结果六周内东山墙处与西部测点的沉降差最大达9cm,且裂缝也在不断开展。可见墙体开裂的主要原因是地基不均匀沉降过大引起的。2事故原因分析根据补充勘探的地质资料显示,该建筑物场地内离东山墙
1 Project Overview A primary school office building, for the five-story brick structure, length 51m, width 11.5m, storey 3.3m, a total construction area of 3053m ~ 2, transverse wall load-bearing, floor prefabricated hollow slab. The basic structure of the lime-soil cushion to do a strip-based foundation, buried depth 1.3m. Before and after the completion of the project, the project found horizontal cracks under the sill of the east wall with a maximum slot width of 7mm. On the bottom of the longitudinal wall near the east wall, there is a narrow slit on the wall and the maximum slot width is 3mm. After the accident, the construction unit, together with the design unit and the testing department, immediately measured the project and recorded the development of the settlement and cracks. Results Within six weeks, the settlement difference between the Dongshan wall and the western measurement point reached a maximum of 9 cm, and fractures were also continuously developing. Can be seen that the main reason for wall cracking is caused by uneven foundation settlement is too large. 2 Analysis of the cause of the accident According to the geological data of the additional exploration shows that the site of the building from the East wall