论文部分内容阅读
为了提高安装桥式起重机的技术水平,缩短工期,保证质量,本文就安装中的几个问题提些看法,供参考。 1.桥式起重机安装必须提前安排安裝其它设备之前应先装好桥式起重机。这样可充分利用它进行设备安装过程中的频繁运输和吊装,提前的时间一般为30天。为了实现这一安排,还需做以下工作: (1)应取得土建施工单位的配合,提前做好行车梁,以供安装轨道; (2)应取得建设单位和制造单位的配合,提前交付桥式起重机成套设备;
In order to improve the technical level of the installation of bridge cranes, shorten the construction period and ensure the quality, this article gives some views on the installation of some of the issues for reference. 1. Bridge Crane Installation Bridge cranes should be installed before other equipment must be arranged in advance. This makes full use of it for frequent transportation and hoisting during the installation of the equipment. The advance time is generally 30 days. In order to realize this arrangement, the following work must be done: (1) The cooperation of the civil construction unit should be obtained, and the traffic beam should be prepared in advance for the installation of the track; (2) The cooperation of the construction unit and the manufacturing unit should be obtained to deliver the bridge in advance. Crane complete sets of equipment;