为什么我们的180搅拌站实际产能都达不到180m~3/h呢?众所周知要想达到180m~3/h产能,就必须每分钟出一盘混凝土,每一盘混凝土是一个生产循环,它分为计量、输送、投料、搅拌、卸料。其中计量和输送时间是可以不计的,因为在连续生产时计量和输送跟搅拌和卸料两个时间是同步的。那么就只剩下三个时间了,投料、搅拌和卸料。以生产C30混凝土为例,搅拌时间30秒是固定的,投料时间20-25秒也是无法改变的,那么就只能在卸料时间上做文章了。我们多数搅拌站的卸料斗就是一个敞开式的大漏斗,由于搅拌车的进料速度有限,为了防止冒料,只能通过搅拌机
Why are our actual production capacity of 180 mixing stations are less than 180m ~ 3 / h? As we all know that in order to achieve 180m ~ 3 / h capacity, it must be out of a plate per minute of concrete, concrete plate is a production cycle, it points For the measurement, transportation, feeding, mixing, unloading. Including measurement and delivery time can be neglected, because in the continuous production of metering and delivery and mixing and unloading of the two time is synchronized. Then only three time left, feeding, mixing and unloading. To produce C30 concrete, for example, the mixing time of 30 seconds is fixed, feeding time is 20-25 seconds can not be changed, then you can only make an issue in the discharge time. Most of our mixing station discharge hopper is an open large funnel, due to the limited feed speed of the mixer, in order to prevent the risk of admissions, only through the mixer