宣化县张全庄金矿是一个日处理能力150t的采、选、冶联合黄金矿山。自1989年4月采用炭浆法提金工艺投料运行以来,我矿依靠科技进步,强化管理,大搞技术改造,促进了生产的发展,取得了较好的经济效益。 一、改造破碎系统 提高生产能力 自改造投产以来,处理量一直达不到设计指标(150t/d)。通过对各种因素的分析和实际考查,认为关键在破碎系统。为此,对
Xuanhua Zhang Quanzhuang gold mine is a daily processing capacity of 150t mining, election, metallurgical joint gold mine. Since April 1989, the Coking Process has been used to feed the gold extraction process. Since then, the mine has relied on scientific and technological progress, intensified management, vigorously promoted technological innovation, promoted the development of production and achieved good economic benefits. First, the transformation of crushing system to improve production capacity Since the transformation and put into operation, the handling capacity has not reached the design index (150t / d). Through the analysis of various factors and the actual test, that the key in the broken system. For that, yes