论文部分内容阅读
在乌山山麓,把漳江上游的水尾、下墩两条溪流拦腰截断,筑起大坝,逼水上山,穿嶂越涧,劈开24座山头,盘绕100多个层峦峻岭,跨越15条溪河,开挖一条85.7公里长的渠道,蜿蜒在秀丽的群峰之中,矫健地飞渡八尺门海峡,把水送进英雄的东山岛。——这就是向东渠。1970年9月动工,1973年3月建成的向东渠引水工程,是云霄、东山两县有史以来规模最大,最为艰巨的建设工程之一,也是当时福建省较大的引水工程。
At the foothills of Wushan Mountain, cut off the two tail streams of the upper reaches of the Zhangjiang River and the lower reaches of the Zhangjiang River, built a dam, forced the water to go up the mountain and cut through 24 streams and cut more than 100 layers of hills and mountains across 15 Strip river, excavation of a channel of 85.7 kilometers long, meandering in the beautiful peaks among the Bifengmen ferocious strait crossing the water, the water into the heroic Dongshan Island. - This is the East Canal. Starting in September 1970 and completed in March 1973, the diversion project to the East Drainage River is one of the largest and most arduous construction projects in Yunxiao County and Dongshan County ever since. It was also the larger water diversion project in Fujian Province at that time.