2016年11月24日7时40分许,江西宜春市丰城发电厂三期在建项目发生冷却塔施工平台坍塌事故,系丰城电厂三期扩建工程D标段冷却塔平桥吊倒塌,造成上面横版混凝土通道坍塌。当时施工单位正在进行零点班和早班交接,现场施工人员有数十人。据了解,丰城电厂三期工程是江西省电力建设重点工程。该冷却塔属于江西丰城电厂三期扩建项目,工程自施工以来,日夜赶工,24小时“三
November 24, 2016 7:40 Xu, Jiangxi Yichun Fengcheng Power Plant Phase III project cooling tower construction platform collapse occurred, the Fengcheng Power Plant Phase III expansion project D flat cooling tower Pingqiao collapse, Resulting in the above horizontal version of the concrete channel collapsed. At that time, the construction unit was carrying out zero-shift classes and early-morning handover, there are dozens of on-site construction workers. It is understood that Fengcheng Power Plant Phase III Project is a key project of Jiangxi Province power construction. The cooling tower belongs to Jiangxi Fengcheng Power Plant Phase III expansion project, since the construction of the project, day and night rush, 24 hours ”three