梅山铁矿二期扩建工程经过设计和建设单位6年艰苦奋斗,2000年底,主体工程基本建成并相继投入使用,经过一年试生产和调整,采、选综合生产能力和质量指标均达到设计要求,2001年12月通过国家验收。梅山铁矿二期扩建工程是国家“八·五”和“九·五”钢铁工业重点建设工程,工程概算投资54152万元,实际投资59231.67万元,该工程总体设计由鞍山冶金设计研究院负责,施工单位,井巷工程由梅山矿业公司自行施工,选矿厂主厂房等工程由中建八局等单位负责。工程建设总规模为年采、选综合生产能力由一期的200万t,扩大到400万t,新增生产规
Meishan Iron Mine Phase II expansion project through the design and construction unit for six years of hard work, the end of 2000, the main project has basically completed and have been put into use, after a year trial production and adjustment, mining, selection of integrated production capacity and quality indicators have reached the design requirements In December 2001 through the national acceptance. The second phase expansion project of Meishan Iron Mine is a key construction project of national “85%” and “95%” steel industry. The project budget investment is 541.52 million yuan and the actual investment is 592.3167 million yuan. The overall design of the project is from Anshan Metallurgy Design and Research Institute is responsible for the construction unit, mine construction by the Meishan Mining Company on their own construction, dressing plant and other projects by the construction of the eight innings and other units. The total construction scale of the project is annual mining, selecting comprehensive production capacity from 2 million tons in the first phase to 4 million tons. The new production regulations