近日,根据省供电总公司统一部署,淮北供电公司完成220千伏及以下地区电网“十三五”滚动规划修编工作。根据滚动规划项目入库结果,淮北市220千伏电网将在2018年至2020年开工建设,220千伏龙湖变、220千伏藕池变和220千伏凌云变,全部采用2×180MVA主变的建设模式。至“十三五”末,三座220千伏变电站的建成将充分满足东部新城的供电需求,有效解决界沟煤矿、杨柳煤矿、童亭煤矿、袁店煤矿、五沟煤矿等重要用户的双电源供电问
Recently, according to the unified plan of the provincial power supply head office, Huaibei Power Supply Company completed the revision of the “13th Five-Year” rolling grid plan of 220kV and below. According to rolling project storage results, Huaibei 220 kV power grid will start construction in 2018 to 2020, 220 kV Longhu change, 220 kV Ouchi change and 220 kV Lingyun change, all using 2 × 180MVA main transformer The building model. By the end of the “13th Five-Year Plan” period, the completion of the three 220kV substations will fully meet the power supply needs of the eastern Metro and effectively solve such major users as Jigou Mine, Yangliu Mine, Tongting Mine, Yuandian Mine and Wuchou Mine Dual power supply asked