潮河上游综合治理工程为司赵至南曹潮河桥到曹古寺水库大坝,全长2.66km。施工完成后,由于工程区内气候多变,造成岸坡形成多条裂缝。文章针对裂缝进行了调查分析,对潮河两岸岸坡裂缝,提出了采取“V”型槽开挖回填法、钻孔灌浆处理等相应的处理措施,以确保河道及堤防运行的安全。
Chao River upstream comprehensive management project for Zhao Zhi Nan Cao Chaohe bridge to the Cao Gu Si reservoir dam, a total length of 2.66km. After the construction is completed, due to the changeable climate in the project area, a number of cracks are formed on the bank slope. According to the investigation and analysis of the cracks, the corresponding measures such as “V” groove excavation and backfill method, drilling grouting treatment and so on are proposed for the bank slope cracks on the Chaohe River so as to ensure the safety of the rivers and embankments.