通过对某特大桥深水基础装配式双壁钢围堰施工的介绍,阐明了利用桩基平台,搭建小型多层内平台,直接在堰内进行围堰拼装、沉放的施工工艺。与借助钢护筒沉放、借助堰外平台吊装的常用方式比,实现了无护筒沉放及护筒的二次周转,大幅减少了桩基护筒投入、缩减了深水平台规模、取消了大型吊装设备。沉放精度更高,施工质量优良,节约了数百万元施工成本。为类似工程提供借鉴与参考。
Through the introduction of the construction of deep-water prefabricated double-walled steel cofferdam of a special bridge, the construction technology of using the pile foundation platform to build a small multi-layer inner platform and directly assembling and depositing the cofferdam in the weir is illustrated. With the use of steel casing, with the weir outside the platform lifting the common way than to achieve a non-casing tube and the second tube casing turnover, a substantial reduction in the pile casing input, reducing the size of the deep-water platform, canceled Large-scale hoisting equipment. With higher precision of deposition and good construction quality, the construction cost of several million dollars has been saved. Provide reference and reference for similar projects.