1.太平驿水电站 太平驿水电站在经过一季度施工低谷后,开始转入正常,各施工承包单位按照监理工程师、建设管理局关于进度计划防洪渡汛等意见,改进施工方案,抓重点,抢工期,重管理,使全工程计划执行情况在二季度较为理想,特别是为今年防洪渡汛安排的防护项目得到落实。如首部枢纽为安全渡汛,已在汛前主要主体工程量(土石方开挖和混凝土浇筑)均超额
1. Taipingyi Hydropower Station Taipingyi hydropower station after the first quarter of construction trough, began to turn normal, the construction contractor units in accordance with the supervision engineer, Construction Authority on the schedule of flood control and other views, improve the construction program, focus, grab the construction period , Heavy management, so that the implementation of the whole project plan in the second quarter is more ideal, especially for this year’s flood protection project flood prevention and control project has been implemented. If the first hub is for flood safety, the main amount of main works (earthwork excavation and concrete pouring) before the flood season are exceeded