工期、成本和质量是风电项目管理的关键。在分析风电项目基建期工期-成本-质量关系的基础上,构建了风电项目工期-成本-质量均衡优化模型,确定了决策变量和效用目标函数,阐述了Pareto蚁群算法的原理和计算步骤,并且通过分析风电工程施工网络计划,计算出关键路径和工期,用MATLAB编写Pareto蚁群算法程序对该模型进行求解得到Pareto解和综合效用值,并生成三维Pareto图,不仅验证了该优化模型的可行性,还为风电项目管理者提供了有效的决策依据。
Duration, cost and quality are the keys to wind project management. Based on the analysis of the construction period-cost-quality relationship of wind power projects, a construction project model of cost-quality balance of wind power project is constructed, the decision variables and utility objective function are determined, the principle and calculation steps of Pareto ant colony algorithm are expounded, And through the analysis of wind power project construction network plan to calculate the critical path and duration, using Pareto ant colony algorithm program written in MATLAB to solve the model to obtain the Pareto solution and the integrated utility value, and generate three-dimensional Pareto graph, not only validated the optimal model Feasibility, but also for wind power project managers to provide an effective basis for decision-making.