论文部分内容阅读
福建省顺昌水泥厂一期工程是国家“七·五”计划重点项目,是利用澳大利亚政府混合贷款,由中央和省合资建设,引进国外八十年代先进技术和设备的现代化工厂,工厂规模为年产硅酸盐水泥62万吨,其中:30万吨熟料运往与之配套的福州粉磨站加工。1986年5月主体工程破土动工,于1988年8月点火投料试生产,1990年12月底通过国家正式
The first phase project of the Shunchang Cement Plant in Fujian Province is a key project of the national “7th Five-Year Plan”. It is a modern factory that uses the Australian Government’s mixed loan, a joint venture between the Central Government and the province, and the introduction of foreign advanced technology and equipment from the 1980s. Annual output of 620,000 tons of Portland cement, of which: 300,000 tons of clinker will be shipped to Fuzhou Grinding Station for processing. In May 1986, the groundbreaking of the main project was started in August 1988, and it passed trial production at the end of December of 1990.