本文论述了群体网络的适用条件和特点,通过电算求出群体工程的最优施工顺序,并在此基础上进行多工程工序衔接的优化调整,最大限度地减少相同工序上的中断现象,保证了施工资源工作的连续性。另外,为了解决多系统群体工程的排序问题,本文利用某工程先期建成的约束条件和相邻工程交换调优法进行妥善处理,从而提高了群体网络的适用性.
This paper discusses the application conditions and characteristics of the community network, calculates the optimal construction sequence of the group project through the computer, and optimizes and adjusts the connection of multiple engineering processes on this basis to minimize the interruption of the same process and ensure The continuity of construction resources work. In addition, in order to solve the problem of sequencing of multi-system community projects, this paper makes use of the constraints of the pre-construction of a certain project and the adjacent engineering exchange adjustment method to properly handle it, thus improving the applicability of the community network.