2010年3月,中国先进研究堆(CARR)工程取得恢复装料许可,5月13日实现首次临界,下半年继续完成堆芯装料并开展B阶段调试工作,在调试过程中逐步完善各系统的性能,B阶段调试工作除中子注量率分布相对测量实验外均已完成;调概报告于年底由院组织审查,修改后即可上报;土建工程竣工结算的审计已经完成,工程规划、消防等项目的单项验收基本完成。在2009年全面完成A阶段调试及改进安全棒驱动机构的基础上,2月份进行新安全棒驱动机构入堆试验,试验结果表明:两套安全棒驱动机构功能及各项技术参数均满足设计和验收大纲的要求。3月22日通过了科工局军核监办组织核安全检查组对CARR进行的恢复装料前专项监督检查,
In March 2010, the China Advanced Research Reactor (CARR) project was granted permission for restoration and loading. The first critical period was achieved on May 13 and the core charge was completed in the second half of the year and B-phase commissioning was carried out. During the commissioning process, the systems were gradually perfected Of the performance, B-phase debugging work in addition to neutron fluence measurement relative to the measurement of the experiment have been completed; the survey report by the end of the hospital organization review, can be submitted after the revision; civil engineering audit completion of the settlement has been completed, engineering planning, Fire and other items of single acceptance basically completed. Based on the complete A-phase commissioning and the improvement of the safety rod drive mechanism in 2009, the new safety rod drive mechanism was put into operation in February. The test results show that the functions and technical parameters of the two safety rod drive mechanisms meet the requirements of design and Acceptance outline requirements. On March 22, the Nuclear Safety Inspection Unit of the Nuclear Surveillance and Inspection Organization of the Bureau of Science and Industry of People’s Republic of China passed a special supervisory inspection of CARR before the restoration and loading.