论文部分内容阅读
混凝土防渗墙为茅坪溪防护坝防渗工程的分项工程,制约着整个工程的工期,工期紧,任务重,施工难度大,质量要求高,最大深度为45m,设计总成墙面积为3.19万m2。监理工程师遵循“守法、诚信、公正、科学”的职业准则,和“公正、独立、自主”的工作准则,以主动控制为主,强调预见性、计划性、指导性和服务性,对混凝土防渗墙施工实行多方位、全过程的跟踪和关键工序旁站监理,保证了工程质量和施工进度,使工程项目建设按合同工期目标要求有序进行。
The concrete cutoff wall is a sub-project of the Maopingxi protective dam seepage control project, which restricts the construction period of the whole project. The construction period is tight, the tasks are heavy, the construction is difficult, the quality is high, the maximum depth is 45m, 31,900 m2. Supervision engineers follow the professional principles of “law-abiding, honest, fair and scientific”, and “fair, independent and autonomous” working principles. They mainly take the initiative to control and emphasize predictability, planning, guidance and service. Permeable wall construction to implement a multi-directional, the whole process of tracking and key processes next to the station supervision, to ensure the quality of the project and the progress of construction, construction projects in accordance with the objectives and requirements of the contract period orderly.