电石厂环氧乙烷装置,经过近二年的建设和生产准备,1994年4月3日进行化工投料试车。经2天紧张地调试运行,4月5日晚,产品纯度达到99.99%。质量达到设计指标,试车一次成功。 设计能力为4万t/a的环氧乙烷装置,1986年7月立项,1990年2月与美国科学设计公司签订技术引进合同,1991年9月开始施工。生产技术由美国科学设计公司提供。基础设计由加拿大福陆·丹尼尔公司完成。吉化设计院进行详细设计和配套设施设计,吉化建设公司进行施工建设。
The calcium carbide plant of the calcium carbide plant has undergone construction and production preparation for the past two years. On April 3, 1994, the chemical feeding test was conducted. After 2 days of intense operation, the purity of the product reached 99.99% on the evening of April 5. The quality reached the design index and the test run was successful. An ethylene oxide plant with a design capacity of 40,000 t/a was established in July 1986. In February 1990, it signed a technology import contract with the American Scientific Design Company. Construction began in September 1991. Production technology is provided by American Scientific Design Corporation. The basic design was completed by Canada’s Fluor Daniel. Jilin Institute of Design conducts detailed design and supporting facilities design, and Jihua Construction Company carries out construction.