某深基坑工程采用地下连续墙加三道内支撑的支护结构,在地下连续墙与钻孔灌注桩施工时.需要大量的泥浆,其中地下连续墙施工泥浆量约14862m~3,钻孔灌注桩施工泥浆量约2966m~3。在施工前,共设置6个大型泥浆池,并在施工中严格控制制浆材料,加大泥浆的循环利用效率,对于回收的泥浆经过沉淀池沉淀后重新拌制再使用,最后废弃的泥浆很少,达到了环保要求。
In a deep foundation pit project, the underground continuous wall and the supporting structure with three inner supports are adopted. During the construction of underground continuous walls and bored piles, a large amount of mud is required, of which the construction slurry for underground continuous walls is about 14862m ~ 3. Pile construction mud volume of about 2966m ~ 3. Before construction, a total of six large mud pool is set, and in the construction of strict control of pulping material, increase the efficiency of slurry recycling, for the recovery of mud sedimentation tank after re-mixing and then use the final waste of mud is Less, meet the environmental requirements.