【案情介绍】某县印刷厂于1998年11月初,在没有提出申请,未取得建设工程规划许可证的情况下,在该厂大门左侧建筑一道高2.2米、长32米的水泥砖围墙。建墙时某县城乡建设委员会城市管理监察大队(以下简称县城管监察大队)曾对县印刷厂的违章行为进行过制止,但该厂没有停止建墙行为。11月21日,县城管监察大队又向县印刷厂发出通知,限令县印刷厂于11月27日以前自行拆除违章建筑的围墙。该厂于同日向县人民政府提交一份“关于要求保留大门
Case introduction A county printing plant in early November 1998, without an application, without the permit of construction projects, the left side of the factory building a 2.2 meters high, 32 meters long cement brick wall. When a wall was constructed, the urban management and inspection team of the county and township construction committee (hereinafter referred to as county management team) had stopped the illegal printing activities of the county printing factory, but the factory did not stop building the wall. On November 21, the county administrative supervision brigade also issued a circular to the county printing plant, ordering the county printing plant to dismantle the walls of illegal structures by November 27. On the same day, the factory submitted to the county people’s government a "Notice of Reservation