目前倒锥形水塔水柜主要有两种施工工艺:一是比较先进的顶升滑模法,施工工期短,高空作业少,但水柜与筒身节点施工较麻烦,需要一套专门设备和专业操作人员,施工费用高,不易推广;二是原始的满堂支架法,水柜与筒身节点连接好,一般施工队即可施工,但模板用量大,高空作业多,劳动强度大,工期长,工人不愿干。装配式永久性钢筋砼模壳施工工艺吸取了两者的长处,克服其不足,且高空作业量少,工期短,
At present, there are two main types of construction technology for the inverted cone water tower water tanks: First, the more advanced lift-up sliding mode method, short construction period, and low-altitude operation, but the construction of water tanks and barrel nodes is more troublesome and requires a special set of equipment and Professional operators have high construction costs and are not easy to popularize; the second is the original full hall bracket method, in which the water tank is connected to the barrel node, and the general construction team can construct it. However, the amount of the template is large, the work at height is high, the labor intensity is strong, and the construction period is long. Workers do not want to do it. The fabricated permanent reinforced concrete formwork construction process absorbs the strengths of both, overcomes its shortcomings, and has a high amount of aerial work and a short construction period.