为提高公寓建造效率的DOC施工法即Day—One Cycle的略称。是为了用定型模板更有效地施工而研制成功的,是立体结构施工法。先把主体结构要施工的作业项目以每天要完成的量分类,随后再把作业工区分类,再按照作业流程,将分了类的作业项目分配至各工区。这样现场工作人员能每天反复地做同一工作。使要在工厂进行的生产工程在现场就能完成。 DOC施工法的计划首先调查出主体结构的作业项目,随后将其分类成每天的工作量。分类例子:分为6类①H(混凝土板)浇灌混凝土②墙配筋,安装外墙预制混凝土板③安装大型模板,V(柱、梁、墙)浇混凝土,走廊,阳台模板安装
The DOC construction method to increase the efficiency of building construction is the abbreviation of Day-One Cycle. It is a three-dimensional structure construction method that has been successfully developed for the purpose of more effective construction with a template. First, the work items to be constructed in the main structure are sorted by the quantities to be completed each day. Then the work areas are classified, and then the classified work items are assigned to each work area according to the work flow. This way, field workers can do the same job repeatedly every day. The production process to be carried out in the factory can be completed on site. The DOC construction method’s plan first investigates the main structure of the project, and then classifies it into daily workload. Classification example: divided into 6 categories 1H (concrete slabs) concrete 2 wall reinforcement, installation of prefabricated concrete slabs 3 installation of large templates, V (column, beam, wall) concrete, corridor, balcony template installation