论文部分内容阅读
摘要:近年来,随着中国经济的快速发展,国民经济对电力供应的需求愈来愈大,国家对电网建设的投入也逐年提高,同时,电力工程对建筑安装的要求也越来越趋向于标准化和精细化。
本文以现实中的实际施工方法为基础,主要以质量、安全和文明施工为立足点,结合行业和社会上客观上对工程建设的各种要求,较为详细的阐述了“角钢塔”这一最普通塔型的施工工艺。
关键词:角钢塔标准化安全质量文明施工
Abstract: In recent years, with the rapid development of the Chinese economy, the national economy is growing demand for electricity supply, the state investment in power grid construction has increased annually, at the same time, the power engineering construction and installation requirements are also a growing tendency to standardization and refinement.This paper take the reality of the actual construction methods as example, mainly in the construction of quality, safety and civilization as a foothold, combined with the various requirements of the engineering construction industry and social objective, a more detailed elaboration of the "angle steel tower, the most the ordinary tower construction process.Keywords: angle steel tower; standardization; safety; quality; civilized construction
中图分类号;TU203 文献标识码:A 文章编号:
一、施工现场组织
1、施工现场人员组织
每个组塔施工现场必须具备以下人员:
2、 施工现场机械设备组织
每个施工现场应具备以下设备:
二、施工现场技术管理
1、 组塔施工流程
本指导书以内悬浮外拉线分解组塔的指导方案。
2、铁塔基础质量复查
2.1 组塔施工前,电气施工对应对铁塔基础半成品保护对基础根开、对角根开、基础预偏、地角螺栓间距或插入角钢倾斜度及插入角钢顶部间距等质量控制点进行复验,确保达到设计要求。
2.2 确保组塔前混凝土强度已达到设计强度的100%,当采取有效防止基础承受水平推力的措施时,混凝土的抗压强度允许不低于设计强度的70%。对基础强度有疑问时,可用回弹仪测试基础强度,达到设计强度时,方可开始组塔。
3、 铁塔材料进场验收
3.1铁塔塔材进入材料站时,由施工项目部会同监理、供货商对进场塔材的镀锌、塔材弯曲度、塔脚焊缝等质量关键点进行验收。
3.2工地材料员应对进入施工现场的铁塔材料进行复查,对照图纸、材料清单对塔材、螺栓、脚钉、垫片等材料数量、规格进行清点检查。
4、施工现场布置
4.1内悬浮外拉线抱杆分解组塔现场布置示意图
1-抱杆拉线;2-抱杆;3-承托绳;4-牵引绳;5-地滑车;6-控制绳;7-吊件;8-起吊滑车组;9-吊点绳;10-卸扣;11-补强木;12-控制地锚;13-抱杆拉线地锚;14-动力地锚。
5、塔材组立
5.1、地面组装
5.1.1对组装有困难的构件应查明原因,不得强行组装。
5.1.2地面组装按照平面布置的要求进行,组装用螺栓、垫片等应按照规格、材质分别堆放,塔材、工器具等定置摆放。
5.1.3螺栓穿向:设计图纸有要求,按照设计要求,设计无要求时,立体结构:
5.2、组立塔脚
5.2.1塔腿组立应根据塔腿质量、根开及地形条件等选择合适的方法。主材较重或者为主角钢插入式基础时宜选用单根吊装;塔腿较轻、地形较平坦且为地脚螺栓式基础时宜选用分片吊装。
5.3 、起立抱杆
5.3.1抱杆采用专用螺栓连接,螺栓数量必须齐全,抱杆按使用要求进行连接,连接后抱杆要正直,不直时可加平垫片调整。
5.3.2若抱杆整立有困难,可以先整立抱杆上部段后,通过倒装提升的方法将下部抱杆段逐节加上。
5.3.3起立过程中后拉线,侧拉线要由专人负责并听从現场负责人指挥。
5.4、抱杆的提升
5.4.1 铁塔组立到一定高度,塔材全部组齐且紧固螺栓后方可提升抱杆。 内悬浮外拉线抱杆提升布置示意图
(1-拉线调节滑车组;2-腰环;3-抱杆;4-抱杆拉线;5-提升钢丝绳;6-已立塔身;7-转向滑车。)
5.4.2提升操作方法
5.4.2.1检查准备工作完毕后,启动绞磨,缓慢牵引提升绳。抱杆提升约1.0m后暂停牵引,将承托绳由塔身主材绑扎点处解开,松挂在主材某节点上,再继续提升。
5.4.2.2抱杆提升过程中,四根外拉线应随之对称、均匀缓慢松出,但不得完全解开,防止抱杆倾倒。
5.4.2.3随着抱杆的提升,承托绳上端应随之向上移动,直至达到预定绑扎点再固定。
5.4.2.4抱杆高出塔体的高度应满足待吊构件能顺利就位。
5.5、塔身吊装
5.5.1塔身的吊装应根据铁塔分段情况采用分片吊装。指挥人员在吊装前应复核吊件重力,不得超重起吊。在起吊过程中,应使吊件靠近已立塔身,距离一般控制在0.3m~0.5m。承力钢索与塔接触处必须要保护措施,防止镀锌破坏。
5.5.2吊件上升时,应设专人监视吊件上升情况,控制绳受力不应过大,松放速度应与吊件提升速度相匹配,防止吊件冲撞塔身。
5.6、横担吊装
对直线塔,根据抱杆承载能力、横担重量和塔位场地条件,可采用整吊或分解吊装。分解吊装时,可将横担分为近塔身侧和远塔身侧两段,近塔身侧段可采用旋转法整体吊装,也可分片吊装。远塔身段可利用地线横担或辅助抱杆整体或分片吊装。
5.7、抱杆的拆除
5.7.1铁塔组立完毕后,抱杆即可拆除。
5.7.2收紧抱杆提升系统,使承托绳呈松弛状态,予可拆除,再将抱杆顶部降到低于铁塔顶面一下,装好铁塔顶部水平塔材。
5.7.3拆除时应采取防止抱杆那倾斜、旋转、摆动的措施,抱杆底部绑扎棕绳,由地面人员引导,防止抱杆冲撞塔身。
5.8、螺栓复紧、脚钉安装与缺陷处理
5.8.1各种螺栓应紧固,达到规范要求的力矩。
5.8.2脚钉应按照设计要求安装在相应塔腿上。脚钉安装后,弯钩应垂直向上成一条直线,不得歪斜。
5.8.3铁塔组立完毕后螺栓应全部复紧一遍,并及时安装防松扣母或防盗螺母,对缺陷逐一处理。
5.9、防腐、防盗、防松
5.9.1全部铁塔构件、插入角钢上端(露出基础部分长加100mm)采用热镀锌防腐。
5.9.2呼称高小于30米的铁塔,横担以下全部使用防盗螺栓,呼称高大于30米的铁塔,30米以下部分使用防盗螺栓,所有防盗销必须在螺栓的垂直上方。
5.9.3所有铁塔导地线挂线角钢两端的连接螺栓均采用双帽。
5.10、铁塔质量自检
5.10.1按照《110kV~500kV架空电力线路工程施工质量及评定规程》所列项目自检。
5.10.2填写自立式铁塔组立检查及评级记录。
主要参考标准:
《110kV~500kV架空送电线路施工及验收规范》
《电力建设安全工作规程 第2部分:架空电力线路》(2009版)
《110kV~500kV架空电力线路工程施工质量及评定规程》
三、施工现场安全管理
1、现场总体安全措施
1.1进入施工现场人员必须经过安全教育,并通过安全考试,熟悉有关安全施工技术措施。
1.2每日开工前列队召开班前会,宣读“一单三卡”交代布置工作任务、告知危险点和安全措施并确认所有人员均已知晓。
1.3进入施工现场必须戴安全帽,穿胶底鞋。
1.4进入现场的安全员、质检员、测量员、架子工、液压人员、高处作业人员等特种作业人员必须持证上岗。
1.5进入施工现场的安全帽、防坠器、安全带等安全防护用品及钢丝绳、链条葫芦、地锚、牵引设备、抱杆、工具袋等工器具应经有试验资质的单位检验合格并经外观检查合格后方可使用。无需进行试验的应经外观检查合格后方可使用,且不得以小代大。
1.6非施工人員不得进入作业区,作业现场除必要的施工人员外,其余人员应离开铁塔设计高度的1.2倍距离以外
1.7施工前应对施工机械仔细检查,确保性能良好正常,施工机械严禁非操作人员操作。
1.8拉绞磨尾绳不得少于两人,距绞磨不得小于2.5m,且不得站在绳圈内。
1.9铁塔组立应设安全监护人(专职安全员)。
2、地面组装安全规定
2.1搬运前应观看周围是否有人及其它障碍,避免互相碰撞,时应注意观察行走道路,避免踩空跌倒。
2.2两人抬运构件时应同肩,并作到同起同落有人接应,多人抬运时步调应一致。
2.3组装场地应平整,障碍物应清除。
2.4严禁将手指伸入螺孔找正。
2.5分片组装时,附件可自由活动,螺帽应平帽。带铁的自由端应绑扎牢固。
2.6组立起第一根主材时应压好接地体。
3、 提升抱杆安全规定
3.1 提升抱杆时,抱杆腰环不得小于两道,应设专人监视抱杆在上升途中有无卡阻现象。
3.2提升时,应根据现场指挥的命令,均匀放出外拉线的尾绳。
3.3吊装安全规定
3.3.1起吊时,塔上人员应站在安全位置,并密切监视塔上滑车及子绳的工作情况,观察被吊塔件是否与塔身相碰。
3.3.2起吊构件的垂直下方不得有人。
3.3.3 起吊钢丝扣与塔材接触位置应垫硬木或麻袋,防止塔件勒坏起吊扣子,吊件接近就位时,牵引速度应减慢,上下密切配合。
3.3.4高空作业所需工器具、材料必须用绳索传递,严禁乱扔,塔上组装所有物品随手放入工具桶内,防止下落伤人。
3.3.5对于塔上不能紧靠的螺栓,应立即解决,以免塔上作业人员搭上抓(踏)空。
四、文明施工管理
1、所有进入施工现场的人员应遵守法律、法规、规程及劳动纪律。
2、全体工作人员均应树立牢固文明施工观念,明确文明施工不仅是安全工作的需要,更是企业形象的标志,作为一种制度,必须严格遵守。
3、施工人员不得与村民、路人发生争执,不得堵塞道路,不得损坏农作物、树木等。如有当地村民进场阻挠施工,应由专门通道协调人员与之解释,其余人员各尽职守专心工作。
4、组塔现场应在安全范围以外设置围栏,非施工人员严禁入内,在醒目位置设置安全警示牌,设专人监护防止行人进入施工现场。
5、施工人员进入现场必须统一服装,佩带上岗证。
6、施工现场各种材料应按段摆放整齐,标识清楚,施工现场应设临时垃圾箱及临时厕所,不得随意倾倒建筑及生活垃圾,不得随地大小便,注意保护环境。
7、应保持施工现场的整洁有序,施工后的施工场地、临时用地、施工损坏的道路、桥梁及其它公用设施应进行清理和修复。
8、施工中应尽量少占农田,应尽量少损坏山林,施工后应尽快回填施工临时地坑。
附: 施工现场安全文明总体布置图
作者简介:王荣生(1955- ),1972年参加工作,工作单位为山东电力集团公司青岛供电公司,现任基建部专责,高压架空线路及电缆方面专家。
牟宗平(1982- ),2005年参加工作,工作单位为青岛恒源送变电工程有限公司,目前从事电力线路专业。
本文以现实中的实际施工方法为基础,主要以质量、安全和文明施工为立足点,结合行业和社会上客观上对工程建设的各种要求,较为详细的阐述了“角钢塔”这一最普通塔型的施工工艺。
关键词:角钢塔标准化安全质量文明施工
Abstract: In recent years, with the rapid development of the Chinese economy, the national economy is growing demand for electricity supply, the state investment in power grid construction has increased annually, at the same time, the power engineering construction and installation requirements are also a growing tendency to standardization and refinement.This paper take the reality of the actual construction methods as example, mainly in the construction of quality, safety and civilization as a foothold, combined with the various requirements of the engineering construction industry and social objective, a more detailed elaboration of the "angle steel tower, the most the ordinary tower construction process.Keywords: angle steel tower; standardization; safety; quality; civilized construction
中图分类号;TU203 文献标识码:A 文章编号:
一、施工现场组织
1、施工现场人员组织
每个组塔施工现场必须具备以下人员:
2、 施工现场机械设备组织
每个施工现场应具备以下设备:
二、施工现场技术管理
1、 组塔施工流程
本指导书以内悬浮外拉线分解组塔的指导方案。
2、铁塔基础质量复查
2.1 组塔施工前,电气施工对应对铁塔基础半成品保护对基础根开、对角根开、基础预偏、地角螺栓间距或插入角钢倾斜度及插入角钢顶部间距等质量控制点进行复验,确保达到设计要求。
2.2 确保组塔前混凝土强度已达到设计强度的100%,当采取有效防止基础承受水平推力的措施时,混凝土的抗压强度允许不低于设计强度的70%。对基础强度有疑问时,可用回弹仪测试基础强度,达到设计强度时,方可开始组塔。
3、 铁塔材料进场验收
3.1铁塔塔材进入材料站时,由施工项目部会同监理、供货商对进场塔材的镀锌、塔材弯曲度、塔脚焊缝等质量关键点进行验收。
3.2工地材料员应对进入施工现场的铁塔材料进行复查,对照图纸、材料清单对塔材、螺栓、脚钉、垫片等材料数量、规格进行清点检查。
4、施工现场布置
4.1内悬浮外拉线抱杆分解组塔现场布置示意图
1-抱杆拉线;2-抱杆;3-承托绳;4-牵引绳;5-地滑车;6-控制绳;7-吊件;8-起吊滑车组;9-吊点绳;10-卸扣;11-补强木;12-控制地锚;13-抱杆拉线地锚;14-动力地锚。
5、塔材组立
5.1、地面组装
5.1.1对组装有困难的构件应查明原因,不得强行组装。
5.1.2地面组装按照平面布置的要求进行,组装用螺栓、垫片等应按照规格、材质分别堆放,塔材、工器具等定置摆放。
5.1.3螺栓穿向:设计图纸有要求,按照设计要求,设计无要求时,立体结构:
5.2、组立塔脚
5.2.1塔腿组立应根据塔腿质量、根开及地形条件等选择合适的方法。主材较重或者为主角钢插入式基础时宜选用单根吊装;塔腿较轻、地形较平坦且为地脚螺栓式基础时宜选用分片吊装。
5.3 、起立抱杆
5.3.1抱杆采用专用螺栓连接,螺栓数量必须齐全,抱杆按使用要求进行连接,连接后抱杆要正直,不直时可加平垫片调整。
5.3.2若抱杆整立有困难,可以先整立抱杆上部段后,通过倒装提升的方法将下部抱杆段逐节加上。
5.3.3起立过程中后拉线,侧拉线要由专人负责并听从現场负责人指挥。
5.4、抱杆的提升
5.4.1 铁塔组立到一定高度,塔材全部组齐且紧固螺栓后方可提升抱杆。 内悬浮外拉线抱杆提升布置示意图
(1-拉线调节滑车组;2-腰环;3-抱杆;4-抱杆拉线;5-提升钢丝绳;6-已立塔身;7-转向滑车。)
5.4.2提升操作方法
5.4.2.1检查准备工作完毕后,启动绞磨,缓慢牵引提升绳。抱杆提升约1.0m后暂停牵引,将承托绳由塔身主材绑扎点处解开,松挂在主材某节点上,再继续提升。
5.4.2.2抱杆提升过程中,四根外拉线应随之对称、均匀缓慢松出,但不得完全解开,防止抱杆倾倒。
5.4.2.3随着抱杆的提升,承托绳上端应随之向上移动,直至达到预定绑扎点再固定。
5.4.2.4抱杆高出塔体的高度应满足待吊构件能顺利就位。
5.5、塔身吊装
5.5.1塔身的吊装应根据铁塔分段情况采用分片吊装。指挥人员在吊装前应复核吊件重力,不得超重起吊。在起吊过程中,应使吊件靠近已立塔身,距离一般控制在0.3m~0.5m。承力钢索与塔接触处必须要保护措施,防止镀锌破坏。
5.5.2吊件上升时,应设专人监视吊件上升情况,控制绳受力不应过大,松放速度应与吊件提升速度相匹配,防止吊件冲撞塔身。
5.6、横担吊装
对直线塔,根据抱杆承载能力、横担重量和塔位场地条件,可采用整吊或分解吊装。分解吊装时,可将横担分为近塔身侧和远塔身侧两段,近塔身侧段可采用旋转法整体吊装,也可分片吊装。远塔身段可利用地线横担或辅助抱杆整体或分片吊装。
5.7、抱杆的拆除
5.7.1铁塔组立完毕后,抱杆即可拆除。
5.7.2收紧抱杆提升系统,使承托绳呈松弛状态,予可拆除,再将抱杆顶部降到低于铁塔顶面一下,装好铁塔顶部水平塔材。
5.7.3拆除时应采取防止抱杆那倾斜、旋转、摆动的措施,抱杆底部绑扎棕绳,由地面人员引导,防止抱杆冲撞塔身。
5.8、螺栓复紧、脚钉安装与缺陷处理
5.8.1各种螺栓应紧固,达到规范要求的力矩。
5.8.2脚钉应按照设计要求安装在相应塔腿上。脚钉安装后,弯钩应垂直向上成一条直线,不得歪斜。
5.8.3铁塔组立完毕后螺栓应全部复紧一遍,并及时安装防松扣母或防盗螺母,对缺陷逐一处理。
5.9、防腐、防盗、防松
5.9.1全部铁塔构件、插入角钢上端(露出基础部分长加100mm)采用热镀锌防腐。
5.9.2呼称高小于30米的铁塔,横担以下全部使用防盗螺栓,呼称高大于30米的铁塔,30米以下部分使用防盗螺栓,所有防盗销必须在螺栓的垂直上方。
5.9.3所有铁塔导地线挂线角钢两端的连接螺栓均采用双帽。
5.10、铁塔质量自检
5.10.1按照《110kV~500kV架空电力线路工程施工质量及评定规程》所列项目自检。
5.10.2填写自立式铁塔组立检查及评级记录。
主要参考标准:
《110kV~500kV架空送电线路施工及验收规范》
《电力建设安全工作规程 第2部分:架空电力线路》(2009版)
《110kV~500kV架空电力线路工程施工质量及评定规程》
三、施工现场安全管理
1、现场总体安全措施
1.1进入施工现场人员必须经过安全教育,并通过安全考试,熟悉有关安全施工技术措施。
1.2每日开工前列队召开班前会,宣读“一单三卡”交代布置工作任务、告知危险点和安全措施并确认所有人员均已知晓。
1.3进入施工现场必须戴安全帽,穿胶底鞋。
1.4进入现场的安全员、质检员、测量员、架子工、液压人员、高处作业人员等特种作业人员必须持证上岗。
1.5进入施工现场的安全帽、防坠器、安全带等安全防护用品及钢丝绳、链条葫芦、地锚、牵引设备、抱杆、工具袋等工器具应经有试验资质的单位检验合格并经外观检查合格后方可使用。无需进行试验的应经外观检查合格后方可使用,且不得以小代大。
1.6非施工人員不得进入作业区,作业现场除必要的施工人员外,其余人员应离开铁塔设计高度的1.2倍距离以外
1.7施工前应对施工机械仔细检查,确保性能良好正常,施工机械严禁非操作人员操作。
1.8拉绞磨尾绳不得少于两人,距绞磨不得小于2.5m,且不得站在绳圈内。
1.9铁塔组立应设安全监护人(专职安全员)。
2、地面组装安全规定
2.1搬运前应观看周围是否有人及其它障碍,避免互相碰撞,时应注意观察行走道路,避免踩空跌倒。
2.2两人抬运构件时应同肩,并作到同起同落有人接应,多人抬运时步调应一致。
2.3组装场地应平整,障碍物应清除。
2.4严禁将手指伸入螺孔找正。
2.5分片组装时,附件可自由活动,螺帽应平帽。带铁的自由端应绑扎牢固。
2.6组立起第一根主材时应压好接地体。
3、 提升抱杆安全规定
3.1 提升抱杆时,抱杆腰环不得小于两道,应设专人监视抱杆在上升途中有无卡阻现象。
3.2提升时,应根据现场指挥的命令,均匀放出外拉线的尾绳。
3.3吊装安全规定
3.3.1起吊时,塔上人员应站在安全位置,并密切监视塔上滑车及子绳的工作情况,观察被吊塔件是否与塔身相碰。
3.3.2起吊构件的垂直下方不得有人。
3.3.3 起吊钢丝扣与塔材接触位置应垫硬木或麻袋,防止塔件勒坏起吊扣子,吊件接近就位时,牵引速度应减慢,上下密切配合。
3.3.4高空作业所需工器具、材料必须用绳索传递,严禁乱扔,塔上组装所有物品随手放入工具桶内,防止下落伤人。
3.3.5对于塔上不能紧靠的螺栓,应立即解决,以免塔上作业人员搭上抓(踏)空。
四、文明施工管理
1、所有进入施工现场的人员应遵守法律、法规、规程及劳动纪律。
2、全体工作人员均应树立牢固文明施工观念,明确文明施工不仅是安全工作的需要,更是企业形象的标志,作为一种制度,必须严格遵守。
3、施工人员不得与村民、路人发生争执,不得堵塞道路,不得损坏农作物、树木等。如有当地村民进场阻挠施工,应由专门通道协调人员与之解释,其余人员各尽职守专心工作。
4、组塔现场应在安全范围以外设置围栏,非施工人员严禁入内,在醒目位置设置安全警示牌,设专人监护防止行人进入施工现场。
5、施工人员进入现场必须统一服装,佩带上岗证。
6、施工现场各种材料应按段摆放整齐,标识清楚,施工现场应设临时垃圾箱及临时厕所,不得随意倾倒建筑及生活垃圾,不得随地大小便,注意保护环境。
7、应保持施工现场的整洁有序,施工后的施工场地、临时用地、施工损坏的道路、桥梁及其它公用设施应进行清理和修复。
8、施工中应尽量少占农田,应尽量少损坏山林,施工后应尽快回填施工临时地坑。
附: 施工现场安全文明总体布置图
作者简介:王荣生(1955- ),1972年参加工作,工作单位为山东电力集团公司青岛供电公司,现任基建部专责,高压架空线路及电缆方面专家。
牟宗平(1982- ),2005年参加工作,工作单位为青岛恒源送变电工程有限公司,目前从事电力线路专业。