以天津永和大桥为背景,介绍了既有PC斜拉桥换索工程中的关键技术问题,包括新索索力的确定、索力控制误差、换索次序及换索工况、换索施工监测方法等。依据换索后的检测结果,介绍了新索索力调整的目标、原则以及计算方法,并对换索后的实际效果进行了分析。永和大桥的换索工程实践表明,换索是改善桥跨结构状态的有效措施。
Taking Tianjin Yonghe Bridge as a background, the paper introduces the key technical problems in cable-stayed cableway replacement of existing PC cable-stayed bridges, including the determination of new cable force, the control error of cable force, the sequence of cable replacement and the condition of cable replacement, Wait. Based on the test results after the changeover, the objectives, principles and calculation methods for the adjustment of the new cable force are introduced, and the actual effect after the changeover is analyzed. The engineering practice of replacing cable in Yonghe Bridge shows that replacing cable is an effective measure to improve the structure of bridge span.